Question

A steel bridge initially costs AED 50 million to construct and will cost AED 200000 per...

A steel bridge initially costs AED 50 million to construct and will cost AED 200000 per year to maintain. Given an interest rate (r), what is the net present value of this scenario? (Assume design life of 25 years).

where, r = 2.70%

Homework Answers

Answer #1

Solution:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.04 million, and the concrete option has an initial cost of $2.5 million. Every 25 years, the steel bridge must be painted at a cost of $450,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
You have four choices. A) To build a “stainless-steel” bridge that will cost you $5 million...
You have four choices. A) To build a “stainless-steel” bridge that will cost you $5 million and last 120 years; or, B) build a regular steel bridge that needs to be replaced after 60 years and today would cost you $4 million and then (in 2020-$) another $4 million in 60 years, or C) build a wooden bridge that costs $3 million and need to be replaced every 20 years (i.e., replaced 5 times to last 120 years) (every time...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.04 million, and the concrete option has an initial cost of $2.5 million. Every 25 years, the steel bridge must be painted at a cost of $450,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
1. A new bridge with a 100-year life is expected to have an initial cost of...
1. A new bridge with a 100-year life is expected to have an initial cost of Birr 20 million. This bridge must be resurfaced every five years, at a cost of Birr 1 million. The annual inspection and operating costs are estimated to be Birr 50 000. Determine the present-worth cost of the bridge using the capitalized equivalent approach (i.e., take the life of the bridge as infinite). The interest rate is 10% per year, compounded annually.
Building a bridge costs $2,000,000,000. and takes 2 years, of this cost, $800 million would be...
Building a bridge costs $2,000,000,000. and takes 2 years, of this cost, $800 million would be spent in year 1, and $1.2 billion in year 2. The bridge yields no benefits during its construction. but starting in year 3, It generates $300 million in benefits a year and costs $100 million a year to maintain. The bridge will last forever. The discount rate is r=0.05. Is this bridge worth building? Please provide detail explanation ( not in handwriting form which...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.04 million, and the concrete option has an initial cost of $2.52 million. Every 25 years, the steel bridge must be painted at a cost of $790,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
Q ) Construction and maintenance of a steel bridge. The fcapital cost is $100 M  and the...
Q ) Construction and maintenance of a steel bridge. The fcapital cost is $100 M  and the bond payoff at year 10 is $50 M. Bond debt service for the first 10 years is $2.5 M per year. Annual O & M for the bridge is $0.5 M and repainting cost every 10 years is $1 M. Using i = 5%. Determine the capitalized cost for the bridge project. $100 M $150 M $0.58 M $161.6M Q) Determine the present worth...
The pumping cost for delivering water from the Ohio River to Wheeling Steel for cooling hot...
The pumping cost for delivering water from the Ohio River to Wheeling Steel for cooling hot rolled steel was $1.8 million for the first 4 years. An effective energy conservation program resulted in a reduced cost of $1.77 million in year 5, and $1.74 million in year 6, and amounts decreasing by $30,000 each year through year 10. What is the present worth of the pumping costs in year 0 at an interest rate of 6% per year? The present...
In order to improve evacuation routes out of New Orleans in the event of another major...
In order to improve evacuation routes out of New Orleans in the event of another major disaster such as Hurricane Katrina, the Louisiana Department of Transportation (L-DoT) is planning to construct an additional bridge across the Mississippi River. The department uses an interest rate of 8% and plans a 50-year life for either bridge. Which design has the better present worth? All costs in $M Bridge M Bridge L Land acquisition $220 $195 Annual O & M 2 3 Annual...
One of two methods must be used to produce expansion anchors. Method A costs $75,000 initially...
One of two methods must be used to produce expansion anchors. Method A costs $75,000 initially and will have a $7,000 salvage value after 3 years. The operating cost with this method will be $36,000 per year. Method B will have a first cost of $105,000, an operating cost of $7,000 per year, and a $46,000 salvage value after its 3-year life. The interest rate for both the methods is 14%. Which method should be used on the basis of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT