Question

A vertical-sided trench was being cut in a very soft clay soil with a density of...

A vertical-sided trench was being cut in a very soft clay soil with a density of about 110 pcf. A depth of 8 ft had been reached when the sides of the trench caved in. Could the trench be completed to a depth of 10 ft by sloping the sides before installing bracing? If so, how steeply may the sides be cut? Show your calculations and sketch the procedure you would follow to complete the job. Apply both the design criteria and the OSHA requirements to this problem.

ANSWER is: Trench will need to be structurally supported. SHOW WORK

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT