Question

EVM For the previous problem, assume that you are at the end of day 5, activity...

EVM

For the previous problem, assume that you are at the end of day 5, activity 10 is 100 percent complete, activity 20 is 66.6 percent complete, and activity 30 is 80 percent complete.

Actual costs:

  • Activity 10: $2,000
  • Activity 20: $900
  • Activity 30: $1,800

Please answer the following questions.

How is the Project Doing? (0.5 point each)

ACWP:

  • BCWS:
  • BCWP:
  • Schedule Variance:
  • SPI:
  • Cost Variance:
  • CPI:

Assessment (1 point):

What do we expect the costs to be at completion? (0.5 point)

  • EAC:

Homework Answers

Answer #1

it

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
At the end of week 24, the project with the data presented in the table below...
At the end of week 24, the project with the data presented in the table below has the earned value right on schedule, but the actual expenses are $9,000. What are the CPI, SPI, CR, ETC, and EAC? Activity Predecessors Duration (weeks) Budget ($) a - 6 900 b - 6 1200 c a 6 1200 d a 12 1800 e b, c 14 1400 f B,c,d 10 1500 g D,e 16 800
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Using the information for Headley Company from the previous problem, now assume there are no market...
Using the information for Headley Company from the previous problem, now assume there are no market constraints for either product, leaving the 250,000 labor hours as the only constraint and that Headley will make optimal use of its labor.  In early November, Headley was invited to bid on a contract to provide 2,000 units of Product B. What is the minimum bid Headley would have to submit in order to breakeven on the contract? Product A                    Product B Per Unit Information: Selling...
From the data shown below, calculate the earned value of each control account as of 5/30/19....
From the data shown below, calculate the earned value of each control account as of 5/30/19. Assume all control account work is on schedule except as noted below. Control Account Scheduled Start Scheduled Completion Budgeted Value EV Progress Rule 1 3/3/2019 6/30/2019 10,000 Percent Complete with Gates (Note 1) 2 5/5/2019 6/6/2019 3,000 Fixed Formula: 50/50 3 5/26/2019 6/6/2019 1,000 Fixed Formula: 0/100 4 5/12/2019 5/30/2019 2,000 Fixed Formula: 30/70 5 4/14/2019 7/11/2019 15,000 Weighted Milestones (Note 2) Note (1):...
1. Metaphor Electronics Inc., a cell phone manufacturing company, manufactures keypads in one process. It also...
1. Metaphor Electronics Inc., a cell phone manufacturing company, manufactures keypads in one process. It also manufactures batteries in a second process and speakers in the third process. These three major subcomponents are assembled together in the final process to manufacture the cell phone. This scenario is an example of _____. sequential processing parallel processing partial processing job-order processing 2. Trux Metals Inc. manufactures a product that passes through three departments: Melting, Skimming, and Molding. In August, the company produced...
You were recently hired by LW’s Bottle Emporium Ltd. (“LW”) as financial controller. LW sells a...
You were recently hired by LW’s Bottle Emporium Ltd. (“LW”) as financial controller. LW sells a high-end set of baby bottles including various sizes to meet the child’s needs throughout their early years. One of your first tasks is to prepare the master budget for the fourth quarter of 2020. To assist you in the preparation of the budget, and supporting schedules, you have been provided with the following information: As of September 30, 2020 LW had the following balance...
1. Aztec Builders allocates manufacturing overhead to jobs based on machine hours. The company has the...
1. Aztec Builders allocates manufacturing overhead to jobs based on machine hours. The company has the following estimated costs for the upcoming year: Direct materials used $25,000 Direct labour costs $62,000 Salary of factory supervisor $50,000 Advertising expense $33,000 Heating and lighting costs for factory $51,000 Depreciation on factory equipment $19,000 Sales commissions $8,000 The firm estimates that 1,800 direct labour hours will be worked in the upcoming year, while 2,000 machine hours will be used during the year. The...
Question 1. (Total: 25 marks) You want to buy a car valued at $48,000. You wi...
Question 1. (Total: 25 marks) You want to buy a car valued at $48,000. You wi ll make an upfront down -payment of $5,000 on the car , and borrow the rest of the money from your bank. Your bank will give you a 5- year loan at 2.5% APR compounded semi -annually . You plan to make biweek ly payments (i.e., one payment every two weeks) on the loan . The bank requires that you make the first payment...
In CVP analysis, the unit contribution margin is: Sales price per unit less cost of goods...
In CVP analysis, the unit contribution margin is: Sales price per unit less cost of goods sold per unit Sales price per unit less FC per unit Sales price per unit less total VC per unit Same as the CM Maroon Company’s CM ratio of 24%.  Total FC are $84,000.  What is Maroon’s B/E point in sales dollars? $20,160 $110,536 $240,000 $350,000       If a firm’s forecasted sales are $250,000 and its B/E sales are $190,000, the margin of safety in dollars is:...