Question

Soil is to be excavated from a borrow pit to construct a 100-m-long trapezoidal levee that...

Soil is to be excavated from a borrow pit to construct a 100-m-long trapezoidal levee that is 3 meters high, 5 meters wide at the top, and 15 meters wide at the base. The in situ total unit weight of the soil in the borrow pit is 21.7 kN/m3 with a water content of 11.4%. If levee construction requires the soil to be placed at a void ratio of 0.47, determine the volume that should be excavated from the borrow pit.

Homework Answers

Answer #1

The volume of soil excavated from borrow pit is 2274.26 m3

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A highway embankment is constructed from soil having a final compacted unit weight of 20.53 kN/m3...
A highway embankment is constructed from soil having a final compacted unit weight of 20.53 kN/m3 and a moisture content of 17.6%. The construction is undertaken by hauling soil from a nearby borrow pit. The soil in the borrow pit has a natural unit weight of 16.29 kN/m3 and a moisture content of 13.2%. Assuming there is no loss of moisture while carrying the soil from the pit to the embankment location, the volume of soil to be excavated from...
At a borrow site, sandy soil was excavated. The soil had a total unit weight (γt)...
At a borrow site, sandy soil was excavated. The soil had a total unit weight (γt) of 124.3 pcf, a water content (ω) of 12.3%, and a specific gravity (GS) of 2.66. The soil was then dried, the maximum and minimum void ratio tests were performed, and eMAX = 0.564 and eMIN = 0.497 were obtained. Determine the relative density of the soil at the borrow site. Assume a volume of solids of 1 ft3.
A compacted earthfill embankment of 50,000 m3 final volume is being constructed as part of a...
A compacted earthfill embankment of 50,000 m3 final volume is being constructed as part of a motorway project. Material for the embankment is to be taken from a borrow pit, where the soil is found to have the following average properties: bulk density 1.940 Mg/m3 , water content 29.5% and specific gravity 2.69. The soil is mechanically excavated and transported in trucks which carry 6 tonnes of soil each when fully loaded. The soil is dumped on the embankment, spread...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT