Question

Given: A = 101° 28’ B = 102° 11’ C = 104° 42’ D = 113°...

Given:

A = 101° 28’

B = 102° 11’

C = 104° 42’

D = 113° 05’

E = 118° 34’

If bearing AB is N 62°30’ E, compute the bearing of DE.

Bearing of DE =

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
*******please don't copy and paste and don't use handwriting **** Q1: Using the below given ASCII...
*******please don't copy and paste and don't use handwriting **** Q1: Using the below given ASCII table (lowercase letters) convert the sentence “welcome to cci college” into binary values. a - 97 b - 98 c - 99 d - 100 e - 101 f - 102 g - 103 h - 104 i - 105 j - 106 k - 107 l - 108 m - 109 n - 110 o - 111 p - 112 q - 113...
A five-sided closed field traverse has the following distances in feet: AB = 647.25; BC =...
A five-sided closed field traverse has the following distances in feet: AB = 647.25; BC = 203.03; CD = 720.35; and DE = 610.24; and EA = 285.13. The interior angles are as follows (measured as angles to the right): A = 100º 45' 37"; B = 231º 23' 43"; C = 17º 12' 59"; D = 89º 03' 28"; and E = 101º 34' 24". The bearing of AB is S 53º 04' 43" E. Determine the bearings of...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 6,600 102 5,280 103 960 $ 3,600 104 4,080 7,200 105 8,400 106 2,900 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 4,100 102 3,200 103 920 $ 2,000 104 2,100 4,500 105 5,700 106 3,800 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
Given the following data. 154 173 119 122 178 246 116 125 113 142 145 119...
Given the following data. 154 173 119 122 178 246 116 125 113 142 145 119 126 117 124 116 115 124 146 118 a) Put the raw data in a data array. b) Give the Five Number summary. c) Compute the InterQuartileRange, Upper Fence, Lower Fence. d) List outlier, if any e) Find the percentile rank of 122 f) Find the score corresponding to 90th percentile.
Given a relation R(A, B, C, D, E) with the following FD Set FD = {...
Given a relation R(A, B, C, D, E) with the following FD Set FD = { A→C, B→C, C→D, DE→A, CE→A} Suppose we decompose it into R1(A, D), R2(A, B), R3(B, E), R4(C, D, E) and R5(A, E), is it a lossless decomposition? Show your proof.
Give the number of core electrons for Se. A) 26               B) 30               C) 28     &nb
Give the number of core electrons for Se. A) 26               B) 30               C) 28               D) 32               E) 34 (1) Which the following orbitals can hold two electrons? A) 3s                                     B) 2px                                                         C) 4dxy D) all of the above                E) none of the above
Observations, using an electronic theodolite were taken in the field for 5 sided polygon traverse, ABCDE....
Observations, using an electronic theodolite were taken in the field for 5 sided polygon traverse, ABCDE. These observations are tabulated below. The coordinates of station A are 1000.000m E, 1000.000 m N. Orienting bearing of leg AB is 73°00’00”. Leg BC is in S.E quadrant. Using these data determine the adjusted coordinates of B, C, D and E applying Bowditch’s rule. Horizontal distance (m) Horizontal Angle (included) Line Length (m) Station Angle AB 51.766 A 101°03’18” BC 26.947 B 101°41’48”...
Given the following information on Events A, B, C, and D. P(A) = 0.35 P(A U...
Given the following information on Events A, B, C, and D. P(A) = 0.35 P(A U D) = 0.55 P(A n D) = 0.12 P(B) = 0.18 P(A I B) = 0.43 P(C) = 0.25 P(A n C) = 0.07 1.Compute P(D). 2.Compute P(A n B). 3.Compute P(A I C). 4.Compute the probability of the complement of C 5. Are events A and C independent? Explain.
Using the formula below, compute P(A|C) using the appropriate table values. P(A|B) = P(A Ç B)...
Using the formula below, compute P(A|C) using the appropriate table values. P(A|B) = P(A Ç B)                                P(B) A B C Totals D .20 .03 .07 .30 E .28 .05 .07 .40 F .22 .02 .06 .30 Totals .70 .10 .20 1.00
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT