Question

Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...

Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s)

Activities Predecessor duration
A - 2
B - 10
C A 9
D A,B 7
E A,B 9
F B 5
G C 10
H D,E 1
I D,E,F 2
J F 7
K C,H,I 2
L I,J 2
M I 1
N G,K 5

Homework Answers

Answer #1

I hope the solution is clear.

Please do comment for further clarification.

If you find this solution helpful, Please give positive rating.

Thank you :)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity  ...
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s) A 10 - D 6 B G 6 E, F B 6 A E 10   B H 6 D C 3 A F 10 C I 2 G, H b) The activities on the critical path are
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D C 1 5 E B 2 5 F E 8 5 G D 10 5 H B 2 5 I B 3 5 J F,G,I 3 5 K H 2 5 L J,K 3 5 M L 1 5 i.Construct an activity on the arrow network ii. Determine the Duration of the Critical Path; iii. Draw the corresponding Gantt chart iv. Draw the resource...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...