Question

Simpson & Brown Company is a pile driving contractor they just received a large project installing...

Simpson & Brown Company is a pile driving contractor they just received a large project installing steel pipe piles they do not want to down time for equipment repairs so the purchased a new Junttan PM 25H hydraulic pile diver for $575,000 a new John Deer 644K loader for $265,000, with trucks and other equipment another $110,000. The seven man crew, fuel, tools, & material, etc. cost $16.19 per lnft of pile installed. They charge $30.00 per lnft of pile installed. How many 60ft steel pipe piles do they have to install to break-even?

Homework Answers

Answer #1

Break even point = ( fixed costs)/( sales per unit price - variable cost per unit)

Here, fixed cost = 575000+265000+110000

= $ 950,000.

Here to find out how many units of 60 feet steel pipes are installed. So, taking 60 feet is a unit.

So, variable cost per unit = 60*16.19 = $971.4

Sales cost per unit = 60*30 = $1800.

Therefore,

Break even point = (950,000)/(1800-971.4)

= 1146.51 units.

So, 114 6.5 1 units of 60 feet steel pipes are installed to get break even point.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT