Question

A concrete mix design requires each cubic yard of concrete to have 1800 lbs dry coarse...

A concrete mix design requires each cubic yard of concrete to have 1800 lbs dry coarse aggregate (density 4400lb/yd3), 615 lbs cement (density 5300lb/yd3), 320 lbs water (density 1680 lb/yd3), and 6% air.

The available aggregates are: coarse aggregate with moisture content of 3.0%, absorption = 1.7%, fine aggregate with moisture content of 3.3%, absorption = 1.9%.

Calculate

a. Required weight of coarse aggregate

b. Required weight of fine aggregate (density 4250 lb/yd3)

c. Required weight of water

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the given data below to calculate the cost for a 1 cubic-meter batch of concrete....
Use the given data below to calculate the cost for a 1 cubic-meter batch of concrete. Note: The data is the result from a concrete mix design. Data: Coarse Aggregate: 2012.85 lb/yd3 Fine Aggregate : 1170.15 lb/yd3 Cement : 612 lb/yd3   Coarse Aggregate Cost: $4,000 per cubic-yard Fine Aggregate Cost : $3,500 per yard cubic-yard Cement Cost : $1,300 per bag and 1 bag of cement = 42.5 kg
) The following recipe was determined as part of a concrete mix design: Water-cement ratio:   0.48...
) The following recipe was determined as part of a concrete mix design: Water-cement ratio:   0.48 Coarse aggregate:        0.60 ft3 CA (bulk volume, dry-rodded) per ft3 concrete Water requirement:    9.6 lbs/ft3 (before moisture corrections) Air content:                5.0% by volume Assuming that the CA and FA to be used in the mix are both at SSD, the moisture content of the CA is 0.5%, the moisture content of the FA is 2.5%, the specific gravity of the CA and FA particles...
7-30 Highway Materials Soils and Concretes A concrete mix contains the following quantities per cubic yard:...
7-30 Highway Materials Soils and Concretes A concrete mix contains the following quantities per cubic yard: cement 516lbs water 273lbs fine aggregate 1355lbs coarse aggregate 1910lbs Calculate the proportions in kg/m^3. find the density in lb/ft^3 and kg/m^3
Concrete is required for an interior concrete column in a commercial building in Corvallis, Oregon. A...
Concrete is required for an interior concrete column in a commercial building in Corvallis, Oregon. A specified compressive strength, f’c , of 4000 psi is required at 28 days using an ASTM C 150 Type I. The design calls for a minimum of 3 in. of concrete cover over the reinforcing steel. The minimum distance between reinforcing bars is 2.5 in. A slump of 4 inches should be the target. No statistical data on previous mixes are available. Follow mixture...
... 00 E H.W 1. Design concrete mix according to ACI with volumetric equation, and calculate...
... 00 E H.W 1. Design concrete mix according to ACI with volumetric equation, and calculate the quantities of concrete ingredients for a slab and 5 bored piles (Show your results in a Table). Average compressive strength required at 28 days = 35 N / mm 'with Slump is (75-100). Dry rodded mass of coarse aggregate is 1600kg / m3. Fineness modulus of fine aggregate is 2.9. the concrete will be exposed to mild waves of freezing and thawing. The...
Calculate the field weights of the ingredients for 0.039 m3 of concrete by using ACI Method...
Calculate the field weights of the ingredients for 0.039 m3 of concrete by using ACI Method of Mix Design. Job specifications dictate the followings:   Cement content: 300 kg/m3 w/c: 0.57 (by weight, from the strength point of view) w/c: 0.53 (by weight, from durability point of view) Fine Aggregate (SSD)/Coarse Aggregate (SSD)=0.45 (by weight) Air Content: 1,30 %   For Fine Aggregate (Crushed): SSD Bulk Specific Gravity: 2.47, Total Moisture: 5,0 % and Absorption Aggregate: 2,7 %.   For Coarse Aggregate (Crushed):...