Question

A 5° curve (measured at the centerline of the inside lane) is being designed for a...

A 5° curve (measured at the centerline of the inside lane) is being designed for a highway with a design speed of 100 km/h. The curve is on a 2% upgrade, and driver reaction time may be taken as 2.5 seconds. What is the closest any roadside object may be placed to the centerline of the inside lane of the roadway while maintaining adequate stopping sight distance?

Homework Answers

Answer #1

SSD = 0.278vt + v2 /254( + x/100)

= 0.278 x 100x2.5 + 1002 /254(0.29 + 2/100) for 100 km/hr, f =0.29

= 196.50 m

Closest any roadside object may be placed to the centerline of the inside lane of the roadway while maintaining adequate stopping sight distance

Mid ordinate

M = R - R cos /2

/2 = (SSD /2R) x 180/π

R = 5730/D = 5730/5

R = 1146

/2 = (196.50 /2x1146) x 180/π

= 4.912

M = R - R cos /2

= 1146 - 1146 cos4.912

= 4.209 m

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A horizontal curve of radius 5620 ft is designed for 60 mph. The roadway is a...
A horizontal curve of radius 5620 ft is designed for 60 mph. The roadway is a 4-lane undivided highway with 12-ft lanes. A tree is located on the inside of the curve only 42 ft from the center of the road. Does it pose a stopping sight distance problem for the drivers travelling at the design speed? Show all supporting calculations.
ou are asked to design a horizontal curve for a two-lane road. The road has 12-ft...
ou are asked to design a horizontal curve for a two-lane road. The road has 12-ft lanes. Due to expensive excavation, it is determined that a maximum of 35 ft can be cleared from the road’s centerline toward the inside lane to provide for stopping sight distance. Also, local guidelines dictate a maximum superelevation of 0.08 ft/ft. Determine the design speed for this curve (mph)?
A horizontal curve is being designed for a new four-lane roadway with 11-ft lanes. The PT...
A horizontal curve is being designed for a new four-lane roadway with 11-ft lanes. The PT is located at station 1050+20, the design speed is 45 mph and maximum superelevation of 4%. If the central angle of the curve is 30 degrees, what is the radius of the curve and location of the PC and PI?
An existing equal-tangent sag vertical curve is designed for 60 mi/h. The initial grade is -3%...
An existing equal-tangent sag vertical curve is designed for 60 mi/h. The initial grade is -3% and the elevation of the PVT is 754 ft. The PVC of the curve is at station 134 + 16 and the PVI is at 137 + 32. An overpass is being constructed directly above the PVI. The highway is for cars only (AASHTO minimum and recommended structure clearances do not apply) and the overpass design assumes the driver's eye height is set conservatively...
An existing equal-tangent sag vertical curve is designed for 60 mi/h. The initial grade is -3%...
An existing equal-tangent sag vertical curve is designed for 60 mi/h. The initial grade is -3% and the elevation of the PVT is 754 ft. The PVC of the curve is at station 134 + 16 and the PVI is at 137 + 32. An overpass is being constructed directly above the PVI. The highway is for cars only (AASHTO minimum and recommended structure clearances do not apply) and the overpass design assumes the driver's eye height is set conservatively...