Question

As a project manager, you have learned, as of the last audit of your project, the...

As a project manager, you have learned, as of the last audit of your project, the project's SPI was 68%, and the project's CPI was 80%. How would you interpret these two parameters? And what would you be your reaction?

Homework Answers

Answer #1

SPI is Schedule Performance Index and CPI is cost performance index both SPI and CPI are efficiency factor regarding project.

SPI depicts ratio of earned value to planned value analyzing schedule efficiency.SPI 68% means earned value is 68% of planned value. SPI is less than one, action is needed to be taken taking project further.

CPI depicts ratio of value of work done to total cost spent for that. CPI 80 means 80% value is achieved CPI less than one means, project is over budget and and it should be looked upon carefully as it it's not proceeding as it should be.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Provide a reflection on what you have learned as you created your project. What would you...
Provide a reflection on what you have learned as you created your project. What would you have done differently? What worked well, and what did not? regarding communication barriers within healthcare?
The PM for the web project left and you have been assigned to manage the project....
The PM for the web project left and you have been assigned to manage the project. The PERT for this project is 30 days and the variance is +/-5 days. There are too many activities on the critical path. The Early Start for task A on the critical path is day 5 and the Late Start is day 7, the Early Finish is day 10, and the Late Finish is on day 15. The CPI is 0.5, but the SPI...
If you are a healthcare manager what post-audit process would you have in place? What would...
If you are a healthcare manager what post-audit process would you have in place? What would you try to achieve? Why is the post-audit critical to good investment decisions?
as a senior project manager and get an Exco notes from the last project manager, how...
as a senior project manager and get an Exco notes from the last project manager, how to Organise the content of your report under headings
You are managing a project to film 5 promotional videos to be posted on youtube. Your...
You are managing a project to film 5 promotional videos to be posted on youtube. Your project has a BAC of $12,000. One of the tasks on the critcal path is to arrange filming locations. The task has a BAC of $2,000. You have confirmed 4 of the 10 locations. The task is scheduled to take 2 weeks (10 days), and it is the end of day 2. You have spent $300 so far. A) identify the tasks BAC, AC,...
You are a Project Manager of a project to build a ten-story building. At the beginning...
You are a Project Manager of a project to build a ten-story building. At the beginning of the project you were targeted to build one floor per month. The planned cost per floor is €500,000. It is now month 8 and you have completed 9 floors and the total costs to date are €4,750,000. Calculate the following: CV; SV; CPI; EAC;
You are a highly regarded project manager at your company. You have demonstrated the ability to...
You are a highly regarded project manager at your company. You have demonstrated the ability to execute and deliver results. You are working on a critical project that has the attention of the CEO. Your project team consists of 25-30 team members where you meet weekly. During a weekly meeting, you learn a team member, Jeff, is withholding information from other team members. Jeff proceeds to throw a tantrum during the meeting and accuses you of misrepresenting his work and...
C. Based on your responses up to this point, what have you learned about the goal...
C. Based on your responses up to this point, what have you learned about the goal of maximizing shareholder value at the U.S. companies? As part of this question, explain how you may use your newly-found knowledge about the goal of the corporations in your work as a future manager.
As a facility manager, what are the steps you would follow in a risk audit and...
As a facility manager, what are the steps you would follow in a risk audit and what are some things you would be looking for?