Question

The Schedule Performance Index relies on________________ and __________________. earned value       forecasted value earned value       planned value...

The Schedule Performance Index relies on________________ and __________________.

earned value       forecasted value

earned value       planned value

earned value       actual value

None of the above

Value Engineering (VE) is aimed at _____________________.

identifying areas of a project where money and resources can be saved

determining the value of a project

All of the above

determining the best value of a project

One of the components of the Cost Management Plan is _______________________.

the level of accuracy of estimating the project’s cost

All of the above

the project’s vendor list

the project’s schedule

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
When looking at the life of a project plan, it is useful to graph and outline...
When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. Execise#2: 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day...
DAU. ACQ. 202. MOD 3. Defense Acquisition University Earned Value Management provides a sound basis for...
DAU. ACQ. 202. MOD 3. Defense Acquisition University Earned Value Management provides a sound basis for (SELECT ALL THAT APPLY) 1.Program Management Plan (PMP) 2.Establishing the Work Breakdown Structure (WBS) 3.Managing the Integrated Master Schedule (IMS) 4.Re-planning the project, if needed 5. Estimating probable completion times and costs 6. Taking corrective action 7. Identifying problems
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the following schedule and cost estimate. What is the budget at completion (BAC) for Ralph’s garage? At the end of week 1, the contractor completed 80% of the footing, framing, and siding. He spent 3,000 on concrete, lumber and vinyl siding. He also paid 1,500 in wages to laborers to complete the footing, framing, and siding. what is the earned value (EV) for Task A...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to turn a major coal fired generating station project around. Currently at 36 percent construction completion, the project is shifting from an emphasis on civil and structural work to bulk production. Cooperation of the owner, the multi-prime contractors, and strong labor unions is cach vital for performance improvement. The analysis of this project involves: 1) identification of significant external influences on the project organization, 2)...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
Funding an IS project through a Chargeback method involves: Pricing the IS service out for the...
Funding an IS project through a Chargeback method involves: Pricing the IS service out for the customer buying the end product Direct billing by the firm for IS resources or services to the department that uses them Direct billing by the manager of a function for IS resources or services to an employee that uses them An accounting process that reduces tax liability for capital investments All of the following are attributes of considering IS costs as Overhead except the...