Estimate the peak flow for a new development area consists of 700 unit houses and a...

Estimate the peak flow for a new development area consists of 700 unit houses

and a market of 25 stalls.

Given:

Dry weather flow = 225 L/day/cap

Residential= 5 PE/unit

Market= 3 per stall

Peak flow = 4.7 x p

-0.11

x 0.0093 m

3

/s

Homework Answers

Answer #1

given :

Dry weather flow = 225L/day/cap

residential = 5 pe / unit

market = 3 per stall

we need to find the peak flow for the new development area

Total number of person from houses/ residential = 5 * 700 = 3500

Total number of person from market = 3 * 25 = 75

peak flow from houses = 225 * 3500 = 787500 L/day

peak flow from market = 225 * 75 = 16875 L/day

Total peak flow (p) = 787500 + 16875 = 804375 L/day

we have to convert L/day into m3/s

[ 1 L = 10-3 m3 ]

[ 1 day = 24 * 60 * 60 seconds ]

therefore, p = 0.0093 m3/s

According to formula,

Peak flow = ( 4.7 * p ) - ( 0.11 * 0.0093 )

putting the value of p, we get:

Peak flow = ( 4.7 * 0.0093 ) - ( 0.11 * 0.0093 )

Peak flow = 0.042687 m3/s

therefore, peak flow for new development area is 0.042687 m3/s

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT