Question

Draw the pressure diagram for a wall form 15 feet tall in which concrete will be...

Draw the pressure diagram for a wall form 15 feet tall in which concrete will be placed at a rate R = 10 feet per hour when the temperature is 60ºF. Draw the diagram if the wall were only 6 feet tall. [Consider Density of concrete = 150 pcf]

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following design conditions for a Wall form system: Concrete Mix = Type III cement...
Given the following design conditions for a Wall form system: Concrete Mix = Type III cement without retarder, Concrete Unit Weight (w) = 150 pcf Wall height (h) = 10 Feet high, Rate of Pour (R) = 8 Feet per hour, Concrete Temperature (T) = 80 Degrees Fahrenheit, Wall Thickness = 12 inches What is the maximum design pressure on the wall in pounds per square foot (psf)? Please solve with all steps and calculations included.
Design forms for 13’-8” high wall to be concreted at the rate of 5 ft per...
Design forms for 13’-8” high wall to be concreted at the rate of 5 ft per hour, internally vibrated. Assume the mix is made with Type I cement, with no pozzolans or admixtures, and that the temperature of concrete at placing is 75°F. The unit weight of concrete is 150 pcf with a slump of 3.75 inches. The forms will be used only once, so short-term loading stresses will apply. Use form grade plywood sheathing 7/8 in. thick in 5×10-ft...
A ladder 25 feet long is leaning against the wall of a house. The base of...
A ladder 25 feet long is leaning against the wall of a house. The base of the ladder is pulled away from the wall at a rate of 2 feet per second. (a) What is the velocity of the top of the ladder when the base is given below? 7 feet away from the wall ft/sec 15 feet away from the wall ft/sec 20 feet away from the wall ft/sec (b) Consider the triangle formed by the side of the...
A 26 foot ladder is lowered down a vertical wall at a rate of 3 feet...
A 26 foot ladder is lowered down a vertical wall at a rate of 3 feet per minute. The base of the ladder is sliding away from the wall. At what rate is the ladder sliding away from the wall when the base of the ladder is 10 feet from the wall? Would you expect the same rate when the ladder is any distance from the wall? Would you expect your answer to be positive when the base is any...
The Assignment: Water at a pressure of 15 bar at a temperature of 30°C enters a...
The Assignment: Water at a pressure of 15 bar at a temperature of 30°C enters a boiler, where it is heated to 250°C at constant pressure. Steam leaving the boiler passes into a throttle which reduces the pressure to 10 bar. The steam is then passed through a small turbine, exiting at atmospheric pressure at 110°C. Please draw a schematic diagram. 1. How much heat is added per kg to the water by the boiler? 2. Find the temperature of...
In answering this set of nine questions, you are encouraged to draw a PV diagram, with...
In answering this set of nine questions, you are encouraged to draw a PV diagram, with P (pressure) on the y axis and V (volume) on the x axis. Plot the three points A, B, and C on this diagram. 1. Consider 10.0 liters of an ideal (monatomic) gas at a pressure of 33.0 atm and a temperature of 326 K. Call this state of the system A. Using the ideal gas law, calculate the number of moles of gas...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead costs are applied to products on the basis of machine hours. The denominator volume of machine hours is 9,000. Standard Quantity or Hours per unit Standard Price or Rate per unit Standard Cost per unit Direct Materials 3 feet $6 per foot $18 Direct Labor 1.5 direct labor hours $10 per direct labor hour $15 Variable Overhead 2 machine hours $12 per machine hour...
Gilmore's Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead...
Gilmore's Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead costs are applied to products on the basis of machine hours. The denominator volume of machine hours is 9,000. Standard Quantity or Hours per unit Standard Price or Rate per unit Standard Cost per unit Direct Materials 3 feet $6 per foot $18 Direct Labor 1.5 direct labor hours $10 per direct labor hour $15 Variable Overhead 2 machine hours $12 per machine hour...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead costs are applied to products on the basis of machine hours. The denominator volume of machine hours is 9,000. Standard Quantity or Hours per unit Standard Price or Rate per unit Standard Cost per unit Direct Materials 3 feet $6 per foot $18 Direct Labor 1.5 direct labor hours $10 per direct labor hour $15 Variable Overhead 2 machine hours $12 per machine hour...
Consider an EOY geometric gradient, which lasts for eight years, whose initial value at EOY one...
Consider an EOY geometric gradient, which lasts for eight years, whose initial value at EOY one is $5500 and g = 6% per year thereafter. For equivalent cash flow, find the equivalent uniform gradient amount, G over the same period if the initial value of the cash flows at the end of year one is $(4500). The interest rate is 10% per year. Write the complete equations used (e.g. P=A(P/A, 12%, 5)+ F(P/F,12%,5)) and substitute the values of the factors...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT