Activity |
Predecessor |
Optimistic |
Normal |
Pessimistic |
A |
None |
2 |
4 |
6 |
B |
None |
3 |
5 |
9 |
C |
A |
4 |
5 |
7 |
D |
A |
4 |
6 |
10 |
E |
B,C |
4 |
5 |
7 |
F |
D |
3 |
4 |
8 |
G |
E |
3 |
5 |
8 |
all possible paths are
S-A-D-F-H
S-A-C-E-G-H
S-B-E-G-H
The critical path is S-A-C-E-G-H
it is expected to take 19.51 weeks to complete the project