Question

1. If a subcontractor’s activity has 5 days of total float, does the subcontractor have the...

1. If a subcontractor’s activity has 5 days of total float, does the subcontractor have the authority to use that float however he/she likes?

2. If the owner adds additional items of work to the project, would this action automatically entitle the contractor to a time extension?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1 he contractor backfilled the foundation before the architect got a chance to inspect the work,...
1 he contractor backfilled the foundation before the architect got a chance to inspect the work, though he had been notified to wait until the architects visit. When the architect arrived on site, he ordered the contractor to dig out the backfill at many places. No defective work was found. Could the contractor claim the cost of removing and repairing the backfill? 2 The architect didn't request to inspect the plumbing rough-in. However, after the drywall had been installed, he...
Why does the scheduling function depend on the planning function? Which one must be done first?...
Why does the scheduling function depend on the planning function? Which one must be done first? Why? Describe what an activity estimated duration is. How is it determined? Why might a contractor prefer to state a project completion time in terms of number of days after the project starts rather than a specific date? Give some examples of instances when this would be appropriate. Why is it important to determine the critical path of a project? What happens if activities...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
1. Mark has a choice of investments; Mark can invest in City of Nowhere Bonds which...
1. Mark has a choice of investments; Mark can invest in City of Nowhere Bonds which pay 6% interest or in Big Bad Corporation bonds that pay 9% interest. Mark has a marginal tax rate of 40%. If both bonds carry the same amount of risk; which bond should he invest in? 2.By the end of year 1, Harold and Jamie Allred had been married for 30 years and have filed a joint return every year of their marriage. Their...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
business ethics Directions: Read each of the following scenarios. Then answer the questions that follow each...
business ethics Directions: Read each of the following scenarios. Then answer the questions that follow each scenario to determine whether the individuals acted ethically. Make sure you provide answers to the questions that are well thought and considerate of all angles and deal directly with the ethics considerations of the problems at hand. Scenario 1 Henry owns a large tract of land in the northern part of the state. For several years, there has been informal talk among lawmakers and...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
In 100 words state if you agree/disagree with the summary made about the adjustments needed for...
In 100 words state if you agree/disagree with the summary made about the adjustments needed for the plan of action. NOTE: Scenario Part 2 is also provided. Work place unrest Part two provides additional information based on talking with your people. Jill: You met Monday afternoon and had a positive and productive discussion. She reiterated what HR had said to me concerning email and talking to Jill. Jill felt she was not challenged job wise and that her and Jack...
Scott's Watermelon Company has the following inputs: Sales = $44,000,000 Total assets on balance sheet =...
Scott's Watermelon Company has the following inputs: Sales = $44,000,000 Total assets on balance sheet = $100,000,000 Total debt in capital structure = $30,000,000 Ke = 15% Kd = 10% (before tax adjustment) Tax rate = 40% The anticipated ongoing net operating income (EBIT) is $17,000,000. With the following data, please tell me what the total fair market value of Scott's Watermelon Company is. Amy's Pet Supply Warehouse is trying to figure out their degree of combined leverage. You aim...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to turn a major coal fired generating station project around. Currently at 36 percent construction completion, the project is shifting from an emphasis on civil and structural work to bulk production. Cooperation of the owner, the multi-prime contractors, and strong labor unions is cach vital for performance improvement. The analysis of this project involves: 1) identification of significant external influences on the project organization, 2)...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT