Question

12. You recently visited the jobsite where the structural concrete pour is still in progress. You...

12. You recently visited the jobsite where the structural concrete pour is still in progress. You had hoped that the structural portion was further ahead than indicated. Your estimate included 100 cubic yards of structural concrete to be placed and 325 man hours for labor. The latest superintendent daily report indicated that 40 cubic yards have been placed to date with an expenditure of 150 man hours. If no changes in work procedure are made, how many remaining work hours will be required to complete the structural concrete placement?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question