12. You recently visited the jobsite where the structural concrete pour is still in progress. You had hoped that the structural portion was further ahead than indicated. Your estimate included 100 cubic yards of structural concrete to be placed and 325 man hours for labor. The latest superintendent daily report indicated that 40 cubic yards have been placed to date with an expenditure of 150 man hours. If no changes in work procedure are made, how many remaining work hours will be required to complete the structural concrete placement?