Question

9. You are the assistant superintendent on the current project. You are getting ready to schedule...

9. You are the assistant superintendent on the current project. You are getting ready to schedule a major concrete foundation pour. The rate of placement has been calculated at 4 vertical feet per hour given the current conditions. The concrete truck will be providing 8 cubic yards per truck. The wall is 18 inches thick, 22 feet high and 150 feet long. How often do you need to schedule the arrival of a concrete truck assuming there will be no problems?

Homework Answers

Answer #1

The dimension of the wall is 18 inch * 22 ft * 150 ft

= 1.5 ft * 22 ft * 150 ft

Of this 22 feet height of wall, 4 ft height of wall should be filled in each hour

So the quantity that has to be filled each hour = 1.5 * 4 * 150 = 900 cub ft

Capacity of each truck = 8 cub yard = 8 * 27 cub ft =216 cub ft

Number of trucks that has to arrive each hour = 900/216 = 4.167

Time that can be taken for the successive arrival of truck = 60min / 4.167 = 14.4 min

So a truck has to arrive at a time gap of 14.4 min inorder to construct the wall at a speed of 4 ft height per hour.

*****If this work helped you, please give a thumbs up and support. Thank you******

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT