Question

The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...

The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV?

Parameter Pessimistic Most Likely Optimistic
Fist cost 150000 100000 80000
Annual benefit 25000 45000 50000
Project life 5 7 9

Homework Answers

Answer #1

Given :

Parameter Pessimistic Most Likely Optimistic
First cost 150000 100000 80000
Annual benefit 25000 45000 50000
Project life 5 7 9

Now we are calculating the expected parameter :

For first cost we are using PERT :

Where, To = Optimistic Time ,Tm = Most Likely TIme ,Tp = Pessimistic time

Therefore ,

Expected First Cost

Annual Benefits at 20% Interest rate

Project Life

Therefore the value of NPV is :

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT