Question

The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...

The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV?

Parameter Pessimistic Most Likely Optimistic
Fist cost 150000 100000 80000
Annual benefit 25000 45000 50000
Project life 5 7 9

Homework Answers

Answer #1

Given :

Parameter Pessimistic Most Likely Optimistic
First cost 150000 100000 80000
Annual benefit 25000 45000 50000
Project life 5 7 9

Now we are calculating the expected parameter :

For first cost we are using PERT :

Where, To = Optimistic Time ,Tm = Most Likely TIme ,Tp = Pessimistic time

Therefore ,

Expected First Cost

Annual Benefits at 20% Interest rate

Project Life

Therefore the value of NPV is :

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions