A compacted earthfill embankment of 50,000 m3 final volume is being constructed as part of a motorway project. Material for the embankment is to be taken from a borrow pit, where the soil is found to have the following average properties: bulk density 1.940 Mg/m3 , water content 29.5% and specific gravity 2.69. The soil is mechanically excavated and transported in trucks which carry 6 tonnes of soil each when fully loaded. The soil is dumped on the embankment, spread and broken up, after which a sprinkler adds water until the water content is 38%. The material is mixed by rotary disc and compacted by sheepsfoot rollers until a dry density of 1.290 Mg/m3 is achieved. P.T.O. 3 Using phase diagrams for 1 m3 of fill, determine the following: (a) Dry density, void ratio and degree of saturation of undisturbed material in the borrow area. [10] (b) Volume of excavation needed in the borrow pit. [4] (c) Number of truck loads required to construct the embankment. [3] (d) Volume of water (litres) to be added per truck assuming losses from evaporation are negligible. [3]
We have used phase diagram to show the required data.
Note here that the data given are not practically correct as explained in the solution.
Get Answers For Free
Most questions answered within 1 hours.