Question

What if the top soil of the site is not removed prior to commencing the construction...

What if the top soil of the site is not removed prior to commencing the construction on site?

Homework Answers

Answer #1

If top soil of the site is not removed prior to construction it leads to following problem or difficulties:

1. Difficult to compact the soil beneath or inner layers.

2.Problem of vegetation in site , structural damages due to vegetation.

3.Problem of chemical wastes that leads to plant growth in soil causing structural damages.

4.soil is soft, loose leads to low for bearing strength for building.

5. Attainment of gradient and drainage conditions in site is difficult.

6.In longtime it leads to settlement of foundation, building due to loose, highly porous and low strength in nature.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
: In a construction site containing only cohesionless soil deposit, how relative density is determined? Also,...
: In a construction site containing only cohesionless soil deposit, how relative density is determined? Also, suggest a remedial method to improve the density index of that site if the relative density is poor.
A 100 CY is removed from an excavated job site, with soils having an expansion rate...
A 100 CY is removed from an excavated job site, with soils having an expansion rate of 33%. Therefore, how CYs of excavated soil will need to be removed from the site? How many 12 CY dump trucks loads would be required to remove the excavated soil from the site? How many cubic yards expanded slab base, with a 33% expansion rate, would need to be ordered to fill a 100 CY hole, with the slab base material compacted to...
For a construction site, describe the importance of accurate survey data. And what would happen if...
For a construction site, describe the importance of accurate survey data. And what would happen if no survey was done prior to the project start? I would really appreciate a typed answer.
how the details of soil exploration are made used to find the soil bearing capacity of...
how the details of soil exploration are made used to find the soil bearing capacity of the construction site.
: Which method of soil test is preferred as an Engineer to determine the density of...
: Which method of soil test is preferred as an Engineer to determine the density of soil in the construction site? What is the difference in the procedure in doing the soil test for determining the dry density and bulk density of soil?
At a borrow site, sandy soil was excavated. The soil had a total unit weight (γt)...
At a borrow site, sandy soil was excavated. The soil had a total unit weight (γt) of 124.3 pcf, a water content (ω) of 12.3%, and a specific gravity (GS) of 2.66. The soil was then dried, the maximum and minimum void ratio tests were performed, and eMAX = 0.564 and eMIN = 0.497 were obtained. Determine the relative density of the soil at the borrow site. Assume a volume of solids of 1 ft3.
What is the purpose and importance of tying rebar together at the construction site?
What is the purpose and importance of tying rebar together at the construction site?
An Engineering consultant appointed on the construction of a Bridge site decided to conduct the Plate...
An Engineering consultant appointed on the construction of a Bridge site decided to conduct the Plate load test to get fair idea about the bearing capacity of the sub soil. The test was conducted on a circular plate of 200 mm radius at a depth of 1.20 m below the natural ground surface in pure clayey soil. The failure took place at a load of 55000N. Calculate the safe bearing capacity of a 1.2 x 1.4 m rectangular footing founded...
Why is soil compaction an important for construction in engineering earthworks?
Why is soil compaction an important for construction in engineering earthworks?
: To design and construct a retaining wall, the Engineer extracted an undisturbed cohesionless soil sample...
: To design and construct a retaining wall, the Engineer extracted an undisturbed cohesionless soil sample from the construction site. Why the engineer collected the undisturbed soil sample? Also discuss how the height of the soil retained and properties of cohesionless soil retained influences the calculation of lateral pressure of soil.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT