Question

The Oregon Department of Transportation (ODOT) released a request for proposals to widening/expanding a certain segment...

The Oregon Department of Transportation (ODOT) released a request for proposals to widening/expanding a certain segment of I-5 between Portland and Salem. The construction work will substantially impact traffic throughout the duration of the project. To minimize the impact of construction on the public, ODOT decided to make a certain arrangement to smooth traffic flow during the construction period of the project. This arrangement will cost ODOT approximately $15,000 per day. Because time is of the essence in this case, ODOT decided to utilize A+B contracts for this project. Three local contractors showed interest in the project and submitted proposals. The table below shows the bid amount and number of proposed days to finish the project. What contractor should ODOT select to be awarded the project? Please show work

Contractor

Bid Amount

# of Days

A

$4,150,000

130

B

$4,400,000

110

C

$4,250,000

115

Homework Answers

Answer #1

In A+B type contracts,

the total bid = A + (B x road user cost per day)

where A = Bid amount and B = 15000 dollars, so calculate the value of total bid for all three contractors as follows

so A values for the contractor A, B and C are 4150000, 4400000 and 4250000 respectively.

So clearly the totalbid for Contractor C is lowest.

So ODOT should choose Contractor C

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT