Question

What are the planning timescales with regards to the construction of significant railway projects?

What are the planning timescales with regards to the construction of significant railway projects?

Homework Answers

Answer #1

● The statutory determination period for validated planning applications is known asplanning timescale.

The timescale for local planning authorities should not exceed :-

​​​​​​1) 8 weeks for straight forward planning,

2) 13 weeks for unusually large or complex planning,

3) 16 weeks if the application is subject to an Environmental Impact Assessment (EIA).

● So beacuse of construction in significant railway projects is comes under the large and complex planning so the planning timescale is 13 weeks for it.

If helpful then give like

thank you.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A railway track will be used for 15 years. During the construction of the railway track...
A railway track will be used for 15 years. During the construction of the railway track line, either type A or type B ties may be used. Type A ties have an installed cost of $6 and a 10-year life; type B will cost $4.50 with a 6-year life. If at the end of 15 years the ties used have a remaining useful life of at least 4 years they will be used elsewhere for a different project and can...
In 4-5 sentences (min) Describe the social changes that railway construction had on British society by...
In 4-5 sentences (min) Describe the social changes that railway construction had on British society by the early 19th century.
What is the effect of globalization and privatization on the marketing of construction projects?
What is the effect of globalization and privatization on the marketing of construction projects?
Construction of Vietnam’s North-South high-speed railway, which allows passengers to travel between capital Hanoi and Ho...
Construction of Vietnam’s North-South high-speed railway, which allows passengers to travel between capital Hanoi and Ho Chi Minh City in about eight hours, will cost about 26 billion U.S. dollars Citing analysis by experts from Germany and the Netherlands, the Ministry of Planning and Investment said that with the span of thousands of kilometers, a running speed of 200 kilometers per hour would be cost-effective, the Vietnam News daily reported. Vietnam may spend 26 billion U.S. dollars to build North-South...
How do construction companies determine how many construction workers to hire for any given projects, is...
How do construction companies determine how many construction workers to hire for any given projects, is it based on the availability of capital and tools? At what point would a construction company determine how many construction workers to hire for any given project? Can you explain how marginal physical product is calculated?
Problem # 1: Assume that as an investor, you are planning to enter the construction industry...
Problem # 1: Assume that as an investor, you are planning to enter the construction industry as a panel formwork supplier. The potential number of forthcoming projects, you forecasted that within two years, your fixed cost for producing formworks is 300,000. The variable unit cost for making one panel is $15. The sale price for each panel will be $25. How many panels you need to sell in total, in order to start making money?
Discuss the use of life-cycle analysis to make decisions on construction projects?
Discuss the use of life-cycle analysis to make decisions on construction projects?
Railway civilengineer What is the effect of selecting different types of sleepers, rail size, and subgrade...
Railway civilengineer What is the effect of selecting different types of sleepers, rail size, and subgrade strength on the granular layer thickness?
The average number of bridge construction projects that take place at any one time in a...
The average number of bridge construction projects that take place at any one time in a certain state is 7. What is the probability that the company will receive 7 property damage claims on a randomly selected day? Answer choices are rounded to the hundredths place. a.)0.44 b.)0.34 c.) 0.14 d.) 0.59
1. Uhrhahn Construction prepared proposals for work on construction projects for Lamar and Joan Hopkins. The...
1. Uhrhahn Construction prepared proposals for work on construction projects for Lamar and Joan Hopkins. The Hopkinses signed the proposals for each project under sections titled “Acceptance of Proposal.” The proposals stated that any changes to the written estimates and specifications had to be in writing. During the construction, the Hopkinses made several oral requests for additional work not included in the proposals. They paid for some of them after receiving invoices labeled change orders for such work. When they...