Curve Number Assignment You need to calculate the curve number for a site which is composed...

Curve Number Assignment You need to calculate the curve number for a site which is composed of: 25 acres industrial buildings, 125 acres 1 acre lots, 60 acres parks/open space with good cover, 40 acres of commercial development, and 225 acres of meadows. The soil was determined to be 50% Sand, 25 % Silt and 25% Clay. a. Determine the Soils Type b. Determine Curve Number for AMC III.

Homework Answers

Answer #1

Given,

Soil Conditions:

50 % Sand

25 % Silt

25 % Clay

Due to the presence of clay in the soil composure, it has very slow infiltration rates when thoroughly wetted.

a) The Soil Type belongs to HSG Group D

b) Curve Number for AMC III:

25 acres industrial buildings --> CN = 93 --> Adjusted CN = 93 * 1 = 93

125 acres 1 acre lots --> CN = 84 --> Adjusted CN = 84 * 1.07 = 89.88 ~ 90

60 acres parks/open space with good cover --> CN = 80 --> Adjusted CN = 80 * 1.14 = 91.2 ~ 91

40 acres of commercial development --> CN = 95 --> Adjusted CN = 95 * 1 = 95

225 acres of meadows --> CN = 78 --> Adjusted CN = 78 * 1.14 = 88.92 ~ 89

Curve Number = = 85.02 ~ 85

Curve Number for a site for AMC III = 85

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT