What is the term used for shortening a logic network after construction has begun?
Crashing |
||
Fast tracking |
||
Resource leveling |
||
Time-scaled network |
||
How is free-float defined?
The amount of slack between activities |
||
The amount of slack within a path of activities |
||
The amount of slack accumulated throughout the logic network |
||
The amount of slack in a node |
The path with the longest sequence of activities in a project plan is called:
Crises |
||
Critical |
||
Concrete |
||
Detailed |
Lead-times are used to determine the estimated time for what type of activity?
Design |
||
Procurement |
||
Construction |
||
Project Closeout |
Question 1) option A is correct,
The method of reducing the project by crashing or reducing time of one or more activity is called crashing
Question 2)option A is correct
Free float is defined as the amount of slack between activities
Question 3) option B is correct ,
Longest path ,time wise in whole network is called critical path
Question 4) option B is correct
Lead time is related to procurement,as follows
Lead time is defined as time required to reorder ,or time taken my shipment to reach the inventory