Question

What is the term used for shortening a logic network after construction has begun? Crashing Fast...

What is the term used for shortening a logic network after construction has begun?

Crashing

Fast tracking

Resource leveling

Time-scaled network

How is free-float defined?

The amount of slack between activities

The amount of slack within a path of activities

The amount of slack accumulated throughout the logic network

The amount of slack in a node

The path with the longest sequence of activities in a project plan is called:

Crises

Critical

Concrete

Detailed

       Lead-times are used to determine the estimated time for what type of activity?

Design

Procurement

Construction

Project Closeout

Homework Answers

Answer #1

Question 1) option A is correct,

The method of reducing the project by crashing or reducing time of one or more activity is called crashing

Question 2)option A is correct

Free float is defined as the amount of slack between activities

Question 3) option B is correct ,

Longest path ,time wise in whole network is called critical path

Question 4) option B is correct

Lead time is related to procurement,as follows

Lead time is defined as time required to reorder ,or time taken my shipment to reach the inventory

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT