Question

#4. Calculate CPI, SPI, CV, SV, ETC, EAC, and % budget overrun and underrun prediction at...

#4. Calculate CPI, SPI, CV, SV, ETC, EAC, and % budget overrun and underrun
prediction at the end of the project with the following data:

BCWS = $90,000
BCWP = $95,000
ACWP = $100,000
Total budget of the project = $200,000

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
We are building a simple storage facility for covered storage of bulk raw materials.   The Budget...
We are building a simple storage facility for covered storage of bulk raw materials.   The Budget is as Follows: The concrete floor is budgeted at $5000. The walls and doors are budgeted at $9000. The roof is budgeted at $5000. The plan is as follows:   The floor will require 2 days to complete, the walls and doors will require 4 days to complete, and the roof will require 2 days to complete. Actual work Complete to Date is as follows:...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
AGENDA: PROFIT PLANNING (BUDGETING) Building a master budget. 1. Sales budget 2. Production budget 3. Direct...
AGENDA: PROFIT PLANNING (BUDGETING) Building a master budget. 1. Sales budget 2. Production budget 3. Direct materials budget 4. Direct labor budget 5. Manufacturing overhead budget 6. Ending finished goods inventory budget 7. Selling and administrative expenses budget 8. Cash budget 9. Budgeted income statement 10. Budgeted balance sheet OVERVIEW OF BUDGETING A budget is a detailed plan for acquiring and using financial and other resources over a specified period. Budgeting involves two stages: • Planning: Developing objectives and preparing...
Exercise 8-3 (Algo) Direct Materials Budget [LO8-4] Four grams of musk oil are required for each...
Exercise 8-3 (Algo) Direct Materials Budget [LO8-4] Four grams of musk oil are required for each bottle of Mink Caress, a very popular perfume made by a small company in western Siberia. The cost of the musk oil is $1.60 per gram. Budgeted production of Mink Caress is given below by quarters for Year 2 and for the first quarter of Year 3: Year 2 Year 3 First Second Third Fourth First Budgeted production, in bottles 90,000 120,000 180,000 130,000...
COURSE PROJECT 1 INSTRUCTIONS You have just been contracted as a new management trainee by Earrings...
COURSE PROJECT 1 INSTRUCTIONS You have just been contracted as a new management trainee by Earrings Unlimited, a distributor of earrings to various retail outlets across the country. In the past, the company has done very little in the way of budgeting and at certain times of the year has experienced a shortage of cash. Since you are well trained in budgeting, you have decided to prepare a master budget for the upcoming second quarter. To this end, you have...
4. The Mycroft Inquiries Group has a price-earnings ratio of 17.5, net income of $194,000, a...
4. The Mycroft Inquiries Group has a price-earnings ratio of 17.5, net income of $194,000, a book value per share of $22.22, and 70,000 shares of stock outstanding. What is its market to book ratio? 5.      Moriarity Ltd has adopted a policy whereby it will maintain a constant debt-equity ratio. Given this, what is its maximum growth rate if it has net income of $9,600, total equity of $66,000, total assets of $150,000 and a 30% dividend payout ratio? 6.     ...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT