Question

What are the durations of these activities? lath and plaster: 1060m2 Painting: external acrylic paint: 907m2...

What are the durations of these activities?

lath and plaster: 1060m2

Painting:

external acrylic paint: 907m2

for plastered walls: 200m2

Homework Answers

Answer #1

1) The quantity that can be completed for 12mm plastering with cement or lime mortar is 8 m2/day.

Therefore time required for plastering of 1060 m2 is

2) The quantity that can be completed for painting is 35 m2/day. Since, there is only a single value for painting with any kind of specification, we calculate it wit hsame reference.

a)External acrylic paint: 907m2

b)Plastered walls: 200m2

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
in a town, 55% of people do sports and 40% paint. 45% of the people in...
in a town, 55% of people do sports and 40% paint. 45% of the people in this town are not interested in such activities at all. Since it is known that a person chosen randomly from the town does sports, what is the possibility of this person painting at the same time?
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
The erection of a steel electrical tower that has 5 levels involves the task durations below....
The erection of a steel electrical tower that has 5 levels involves the task durations below. Each of the 5 levels must have its steelwork erected, have stabilising wires connected and then be painted. After all the 5 levels are completed, the electrical wires will be connected to the top of the tower: Erect one level of steelwork = 2 days Connect the stabilising wires to one level of steelwork = 3 days Paint one level of steelwork = 2...
In printmaking, when an edition is complete, what will typically happen to the matrix? Multiple Choice...
In printmaking, when an edition is complete, what will typically happen to the matrix? Multiple Choice It will be registered so that the edition may be copyrighted. It will be registered so that the artist may rework his or her ideas anew. It will be restored so that a new image may be printed from it. It will be canceled so that no more prints can be made from it. For what purpose was color photography first widely used? Multiple...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
The Nataraj Metal Products Company (hereinafter referred to as the Nataraj), has it manufacturing plant at...
The Nataraj Metal Products Company (hereinafter referred to as the Nataraj), has it manufacturing plant at Arani and employs about 500 workers. It produces a variety of metal products such as brass knobs, steel frames, collapsible iron gates, chromium handles and so on. Orders for these are placed by building contractors in and around Madras but the volume of orders fluctuates, with the rainy season being the slowest period. The company is reputed for quality products delivered on time and...
PRODUCTION PLANNING AT VIKTOR LENAC SHIPYARD Professor Giorgio Sinković and Professor David M. Currie prepared this...
PRODUCTION PLANNING AT VIKTOR LENAC SHIPYARD Professor Giorgio Sinković and Professor David M. Currie prepared this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be transmitted, photocopied, digitized, or otherwise reproduced in any form or by any means without the permission of the copyright holder. Reproduction...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT