Question

Consider a clay layer that is 1 m thick. The clay has a compression index of...

Consider a clay layer that is 1 m thick. The clay has a compression index of 0.35, a swell index of 0.07, a permeability of 4 x 10-7 cm/sec, a preconsolidation pressure of 172 kPa and a coefficient of consolidation of 2.7 x 10-4 cm2/min. The initial effective stress at the midpoint of the layer is 140 kPa, and the soil has a void ratio of 1.01. The stress is increased to 200 kPa. The soil is drained above and below. The total primary consolidation expected is 4.40 cm.

a) How much time in days is required for 2.0 cm of primary settlement to occur?
b) What percentage of consolidation will have occurred after 1 year?  

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider a 20 foot thick saturated clay that has a sand layer above it and an...
Consider a 20 foot thick saturated clay that has a sand layer above it and an impermeable rock layer below it. The clay layer has an initial effective stress at its midpoint of 3145 lbs/ft2.    Due to the presence of a large water tank on the surface, the stress is increased by 710 lbs/ft2 at the midpoint of the clay layer. How much total settlement from primary consolidation is expected? Provide your answer in inches. Soil properties: Compression index = .324,...
A 10-ft-thick silty clay layer is subjected to a load that results in total primary consolidation...
A 10-ft-thick silty clay layer is subjected to a load that results in total primary consolidation settlement of 0.85 inches. The clay is sandwiched between two sand layers and has an initial void ratio of 0.76, a coefficient of compression of 0.45, a coefficient of recompression of 0.07 and a coefficient of consolidation of 0.034 in2 /year. Calculate the settlement at the end of 2 years and determine the time in days for 0.60 inches of settlement.
A 10-ft-thick silty clay layer is subjected to a load that results in total primary consolidation...
A 10-ft-thick silty clay layer is subjected to a load that results in total primary consolidation settlement of 0.85 inches. The clay is sandwiched between two sand layers and has an initial void ratio of 0.76, a coefficient of compression of 0.45, a coefficient of recompression of 0.07 and a coefficient of consolidation of 0.034 in2/year. Calculate the settlement at the end of 2 years and determine the time in days for 0.60 inches of settlement.
The ultimate consolidation of a 13-ft thick single-drained clay layer (cv = 0.1 ft2/day) was calculated...
The ultimate consolidation of a 13-ft thick single-drained clay layer (cv = 0.1 ft2/day) was calculated to be 0.813 feet. a. What is the average degree of consolidation for the clay layer when the settlement is 2 inches? b. If the average value for cv for the pressure range is 0.003 cm2/second how long will it take for 50% settlement to occur? (be careful on the units) c. If the 17 ft clay layer is drained on one side, how...
A layer of clay, 4 meters thick will settle a total of 57 mm under a...
A layer of clay, 4 meters thick will settle a total of 57 mm under a new applied load. Determine how much settlement will occur within the first year if the coefficient of consolidation is 0.07 cm2/min and the soil can only drain from the top. Provide your answer in millimeters as a whole number.
An embankment will be filled at a site. Before filling the embankment, a soil specimen with...
An embankment will be filled at a site. Before filling the embankment, a soil specimen with a height of 20mm is sampled from the middle of a normally consolidated clay which has a thickness of 4 m. A consolidation test reveals that the soil has a pre-consolidation pressure of 120 kPa, compression index Cc = 0.16, initial void ratio of 0.85. (1) If the settlement of the clay layer is 38.6 mm due to the extra loading from the embankment,...
The net stress increase due to a building at the middle of a 6 ft normally...
The net stress increase due to a building at the middle of a 6 ft normally consolidated clay layer is 400 psf. The compression index of the soil is 0.6 and its void ratio is 1.3. If the primary consolidation settlement is 2.34 inch, the initial effective consolidation stress (psf) is most nearly equal to a) 1400 b) 1200 c) 1000 d) 1600 Please show all steps
Using the data in Textbook Problem 8.8: a. Plot the vertical effective consolidation stress versus void...
Using the data in Textbook Problem 8.8: a. Plot the vertical effective consolidation stress versus void ratio on both arithmetic and semi-log graphs. For the arithmetic graph, constrain the vertical axes to 0.55 and 0.95; and the horizontal to 0 to 1,500 kPa; for the semi-log graph, use the same vertical axis constraints, but use 10 kPa and 10,000 kPa to ease interpretation. Plot the data points only, and draw in a smooth curve by hand. Plot each graph on...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT