in an emulsion polymerization, all the ingredients are charged at time t=0. The time to convert various amounts of monomer to polymer is indicated in the following table. Predict the time for 30% conversion. Polymerization is nomal.(no water solubility or polymer percipitation)
Fraction of original charge of monomer converted to polymer time(hr)
0.05 2.2
0.12 4.0
0.155 4.9
charging time of ingredients=t=0 is the starting time of reaction/charging,
the chart shows ,
0.05 =2.2 hrs for 100% conversion,
0.12 =4.0 hrs for 100% conversion,
0.155 =4.9 hrs for 100 % conversion,
now we will calculate the times for 30% conversion,
1) 0.05*30=1.5/100=0.015 ,
if 0.05 =2.2 hrs. then for
0.015=?, by cross multiplying we can get the time require for 30%,
0.015*2.2=0.033/0.05=0.66 hrs,
2) if 0.12= 4.0 for 100%,
0.12*30=3.6/100=0.036 (30%),
0.12 = 4 hrs,
0.036=?, ,
0.036*40.144/0.12=1.2 hrs,
3) if 0.155 =4.9 hrs for 100%, then for 30%= ?,
0.155*30=4.65/100=0.0465,
0.155=4.9 hrs then,
for 0.0465=?,
0.0465*4.9=0.2278/0.155=1.47 hrs