Question

Find the critical path and the project completion time for the following list of activities. Calculate...

Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10

I do not understand how you are coming up with the answers. I understand the concept. I know how the teacher explained it but the examples to the problems are not making sense. they all have different answers.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
Use the following activities and their three duration estimates (in days) to do the following Determine...
Use the following activities and their three duration estimates (in days) to do the following Determine the expected duration of the project – use 2 decimals when determining the duratio Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
The critical path for the network activities shown below is ________ with duration ________. Activity Duration...
The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 2 A C 7 -- D 4 A E 5 B,C,D
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 6 C A,B 7 D A,B 6 E A,B 8 F C,D,E 4 G C,D,E 3
HW8-Ch2-Executing Strategy: Project Management 1. A computer-system installation project consists of eight activities. The immediate predecessors...
HW8-Ch2-Executing Strategy: Project Management 1. A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are as follows: Activity Immediate Predecessors Activity Time A — 2 B — 7 C A 3 D A, C 6 E C 5 F D, E 2 G B, C 10 H G 4 What is the critical path? What is the project complete time? a. BCDEF; 22 weeks b. ACEF; 23 weeks c. BGH; 21 weeks 2....
The R&D Department is planning to bid on a large project for the development of a...
The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes.  The accompanying table shows the activities, times, and sequences required: Activity Immediate Predecessor Optimistic Most Likely Pessimistic A - 3 6 8 B A 2 4 4 C A 1 2 3 D C 6 7 8 E B,D 2 4 6 F B 6 10 14 G E, F 1 2 4 H F 3 6 9 I...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...