Question

The cost of direct materials transferred into the Rolling Department of Oak Ridge Steel Company is...

The cost of direct materials transferred into the Rolling Department of Oak Ridge Steel Company is $546,000. The conversion cost for the period in the Rolling Department is $318,150. The total equivalent units for direct materials and conversion are 3,000 tons and 5,050 tons, respectively.

Determine the direct materials and conversion costs per equivalent unit.

Direct materials cost per equivalent unit: $ per ton
Conversion cost per equivalent unit: $ per ton

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Cost per Equivalent Unit The cost of direct materials transferred into the Rolling Department of Kraus...
Cost per Equivalent Unit The cost of direct materials transferred into the Rolling Department of Kraus Company is $485,000. The conversion cost for the period in the Rolling Department is $291,200. The total equivalent units for direct materials and conversion are 2,500 tons and 4,550 tons, respectively. Determine the direct materials and conversion costs per equivalent unit. Direct materials cost per equivalent unit: $ per ton Conversion cost per equivalent unit: $ per ton
Cost per Equivalent Unit The cost of direct materials transferred into the Rolling Department of Kraus...
Cost per Equivalent Unit The cost of direct materials transferred into the Rolling Department of Kraus Company is $451,200. The conversion cost for the period in the Rolling Department is $289,750. The total equivalent units for direct materials and conversion are 2,400 tons and 4,750 tons, respectively. Determine the direct materials and conversion costs per equivalent unit. Direct materials cost per equivalent unit: $ per ton Conversion cost per equivalent unit: Cost of Units Transferred Out and Ending Work in...
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons...
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons in beginning work in process inventory (60% complete) on July 1. During July, 52,500 tons were completed. The ending work in process inventory on July 31 was 2,600 tons (30% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 10,800 tons...
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 10,800 tons in beginning work in process inventory (30% complete) on July 1. During July, 67,800 tons were completed. The ending work in process inventory on July 31 was 3,400 tons (70% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
1. The Rolling Department of Kraus Steel Company had 2,442 tons in beginning work in process...
1. The Rolling Department of Kraus Steel Company had 2,442 tons in beginning work in process inventory (20% complete) on October 1. During October, 40,700 tons were completed. The ending work in process inventory on October 31 was 3,663 tons (20% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. ______units 2. The cost of direct materials transferred into the Rolling Department of Kraus Company is $518,400. The conversion cost for the period...
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,523 tons...
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,523 tons in beginning work in process inventory (10% complete) on July 1. During July, 59,300 tons were completed. The ending work in process inventory on July 31 was 4,744 tons (60% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit.
1. The costs per equivalent unit of direct materials and conversion in the Rolling Department of...
1. The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $1.65 and $0.25, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 0 3,100 Started and completed during October 52,000 52,000 Transferred out of Rolling (completed) 52,000 55,100 Inventory in process, October 31 3,000 1,200 Total units to be assigned costs 55,000 56,300 The beginning work in process...
The cost of materials transferred into the Rolling Department of Keystone Steel Company is $535,900 from...
The cost of materials transferred into the Rolling Department of Keystone Steel Company is $535,900 from the Casting Department. The conversion cost for the period in the Rolling Department is $105,600 ($63,400 factory overhead applied and $42,200 direct labor). The total cost transferred to Finished Goods for the period was $603,000. The Rolling Department had a beginning inventory of $29,600. a1. Journalize the cost of transferred-in materials. a2. Journalize the conversion costs. If an amount box does not require an...
Process Cost Journal Entries The cost of materials transferred into the Rolling Department of Keystone Steel...
Process Cost Journal Entries The cost of materials transferred into the Rolling Department of Keystone Steel Company is $593,800 from the Casting Department. The conversion cost for the period in the Rolling Department is $113,900 ($65,600 factory overhead applied and $48,300 direct labor). The total cost transferred to Finished Goods for the period was $666,400. The Rolling Department had a beginning inventory of $25,400. a1. Journalize the cost of transferred-in materials. a2. Journalize the conversion costs. If an amount box...
Process Cost Journal Entries The cost of materials transferred into the Rolling Department of Keystone Steel...
Process Cost Journal Entries The cost of materials transferred into the Rolling Department of Keystone Steel Company is $571,500 from the Casting Department. The conversion cost for the period in the Rolling Department is $109,000 ($67,700 factory overhead applied and $41,300 direct labor). The total cost transferred to Finished Goods for the period was $607,000. The Rolling Department had a beginning inventory of $25,900. a1. Journalize the cost of transferred-in materials. a2. Journalize the conversion costs. If an amount box...