Question

A plant has 4 operators to be assigned to four machines. the time (minutes) required by...

A plant has 4 operators to be assigned to four machines. the time (minutes) required by each worker to produce a product on each machine is shown in the following table"

Determine the optimal assignemnt and compute total minimum time.

Machine
Operator A B C D Supply Assigned
1 0 0 1 0 1
2 1 0 0 0 1
3 0 1 0 0 1
4 0 0 0 1 1
Demand 1 1 1 1 4
Assigned
Total time = 37
Time (mins):
Machine
Operator 1 2 3 4
1 10 12 9 11
2 5 10 7 8
3 12 14 13 11
4 8 15 11 9

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in...
Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in the table below. Perform the assignment method. What is the optimal assignment? Machine A Machine B Machine C Job 1 11 14 6 Job 2 8 10 11 Job 3 9 12 7
The following are number of mistakes made on five occasions by word processor operators setting a...
The following are number of mistakes made on five occasions by word processor operators setting a technical report. Operator 1: 10 13 9 11 12 Operator 2: 11 13 8 16 12 Operator 3: 10 15 13 11 15 Operator 4: 15 7 11 12 9 Perform an analysis of variance and decide at the 0.01 level of significance whether the differences among the four sample means can be attributed to chance. State the conclusion.
A trauma center keeps ambulances at locations throughout the east side of a city in an...
A trauma center keeps ambulances at locations throughout the east side of a city in an attempt to minimize the response time in the event of an emergency. The times in minutes, from ambulance locations to population centers are given in the table below. POPULATION CENTERS AMBULANCE LOCATIONS EAST NORTHEAST SOUTHEAST CENTRAL Site 1 8 9 12 13 Site 2 9 11 10 8 Site 3 12 14 12 11 Site 4 15 12 13 9 Find the optimal assignment...
Create a graph to represent the data. What graph is best to use? Time (minutes) Part...
Create a graph to represent the data. What graph is best to use? Time (minutes) Part A (Positive Control) Part B Part C (Dark) Part D (Natural sunlight) 1 2 0 1 0 2 3 0 1 1 3 5 0 1 2 4 7 0 0 4 5 8 0 0 6 6 8 0 0 9 7 8 0 0 9 8 8 0 0 10 9 9 0 0 10 10 9 0 0 10 11 9...
make a box plot explaining the Variations that affect the lead time of serving a hot...
make a box plot explaining the Variations that affect the lead time of serving a hot coffee. Number of Customer Order Time (minutes) Preparation time (minutes) 1 3 11 2 5 11 3 4 12 4 5 13 5 5 12 6 4 9 7 3 7 8 3 9 9 4 10 10 5 11 11 3 7 12 4 14 13 5 13 14 2 8 15 3 10 16 5 12 17 4 10 18 3 9...
You love the new elliptical machines your gym added several months ago, but because they are...
You love the new elliptical machines your gym added several months ago, but because they are so popular with other members too, you usually have to wait for a machine to become available. Out of curiosity, each day you write down how many minutes you have to wait for an elliptical machine. Using a confidence level of 80%, is the average wait time for an elliptical machine less than 5 minutes? 2 0 5 7 5 8 5 5 10...
Determine the time required to perform the following activities. Using the predetermined time method MOST. Report...
Determine the time required to perform the following activities. Using the predetermined time method MOST. Report the total time in TMU and seconds. A. An operator walks 8 steps takes a handful of packages of different sizes of a table then walks 10 steps, passes through a door and walks three steps place the packages on a ledge. B. The same operator from the position that is, walks 9 steps and start a machine operating for 4 seconds, with movement...
Part 5.   Questions 8,9. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...
Part 5.   Questions 8,9. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1st,2nd,3rd, for A,B,C, respectively.] Consider the jobs scheduled on two machines in the order of (A,B,C) where each job is started as soon as possible. The processing times for each job on each machine are given in the table below. Assume time on machine #1 is represented with “(1)” and on machine #2 with “(2)”. Job Machine#1 Time Machine#2 Time...
An industrial engineer is investigating the effect of four assembly methods (A, B, C, and D)...
An industrial engineer is investigating the effect of four assembly methods (A, B, C, and D) on the assembly time for a color television component. Four operators are selected for the study. Furthermore, the engineer knows that each assembly method produces such fatigue that the time required for the last assembly may be greater than the time required for the first, regardless of the method. To account for this source of variability, the engineer uses the design below. explain the...
An industrial engineer is investigating the effect of four assembly methods (1, 2, 3, 4) on...
An industrial engineer is investigating the effect of four assembly methods (1, 2, 3, 4) on the assembly time for a color television component. Four operators are selected for the study. To account for the operator source of variability, the engineer uses the Randomized Complete Block Design shown below. Analyze the data from this experiment ( = 0.05) draw appropriate conclusions. Assembly Operator Method A B C D 1 5 10 7 8 2 7 10 12 8 3 12...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT