Question

The following table lists the components used in assembling item FG-A. The following information is also...

The following table lists the components used in assembling item FG-A. The following information is also included for each component: lead time, the on-hand supply, and direct components.

Item

Lead Time (days)

Available Inventory

Direct Components

FG-A

1

0

SA-B(1), SA-C (2), SA-D(2)

SA-B

1

0

SA-D(2)

SA-C

2

0

E (1), F(2)

SA-D

2

0

E(3)

E

1

10

---

F

3

5

---

  1. Construct a product structure tree at a lowest level coding.
  2. Prepare a time-phased product structure.
  3. Given the information above, show the quantities needed for 15 units of FG-A for each of the following 5 components: SA-B, SA-C, SA-D, E and F.
  4. If we wanted to make ONE FG-A, would we need to order any more of either E or F? Why/why not?
  5. What is the total lead time (in days) associated with making an item of FG-A, assuming we had NO starting on-hand inventory for any component?

Homework Answers

Answer #1

i can only do 4 parts

but i did answered e too

for any doubt comment

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item lead time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
Product A is made from components B and C. Item​ B, in​ turn, is made from...
Product A is made from components B and C. Item​ B, in​ turn, is made from D and E. Item C also is an intermediate​ item, made from F and H.​ Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead​ times: Item A B C D E F G H Lead Time​ (weeks) 1 1 2 2 6 4 4 6 a. What lead time​ (in weeks)...
Product A is assembled from 6 components. The components are B, C, D, E, F, G....
Product A is assembled from 6 components. The components are B, C, D, E, F, G. Components B, D, and F are purchased from a supplier, complete and ready to assemble. Component C is assembled from parts H, I, and J. Component E is assembled from parts K and L. Component G is made in the plant from raw materials. Part H is made from parts M and N. Part L is made from parts P, Q, and R. Part...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks. Item D 1 2 3 4 5 6 Gross Requirements 100 300 100 400 100 50 On Hand/ Scheduled Receipts 700 Net Requirements A Planned Order Releases B The value of entry A is: A. 100 B. 200 C. 300 D. 700 E. None of the above. Reset Selection Question 19 Product D...
The demand for subassembly S is 120 units in week 7. Each unit of S requires2...
The demand for subassembly S is 120 units in week 7. Each unit of S requires2 units of T and 1 unit of U. Each unit of T requires 1 unit of​ V,1unit of​ W, and1 unit of X.​ Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make​ S,1week to make​ T, 2 weeks to make​ U, 2 weeks to make​ V, 3...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 57 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
Marco Enterprises manufactures one of the components used to assemble its main company product. Specialty​ Products,...
Marco Enterprises manufactures one of the components used to assemble its main company product. Specialty​ Products, Inc., has offered to make the component at a cost of $13.10 per unit. Marco ​Enterprises' current cost is $14.75 per unit of the​component, based on the 105,000 components that Marco Enterprises currently produces. Read the requirements LOADING... . This current cost per unit is based on the following​ calculations: LOADING... ​(Click the icon to view the​ information.)None of Marco ​Enterprises' fixed costs will...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT