Problem 4-17
Frandec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers. One product, called a Liftmaster, is assembled from four components: a frame, a motor, two supports, and a metal strap. Frandec’s production schedule calls for 5000 Liftmasters to be made next month. Frandec purchases the motors from an outside supplier, but the frames, supports, and straps may be either manufactured by the company or purchased from an outside supplier. Manufacturing and purchase costs per unit are shown.
Component | Manufacturing Cost | Purchase Cost |
Frame | $38.00 | $51.00 |
Support | $11.50 | $15.00 |
Strap | $6.50 | $7.50 |
Three departments are involved in the production of these components. The time (in minutes per unit) required to process each component in each department and the available capacity (in hours) for the three departments are as follows:
Department | |||
Component | Cutting | Milling | Shaping |
Frame | 3.5 | 2.2 | 3.1 |
Support | 1.3 | 1.7 | 2.6 |
Strap | 0.8 | — | 1.7 |
Capacity (hours) | 350 | 420 | 680 |
Let | |
FM = number of frames manufactured | |
FP = number of frames purchased | |
SM = number of supports manufactured | |
SP = number of supports purchased | |
TM = number of straps manufactured | |
TP = number of straps purchased |
Min | FM | + | FP | + | SM | + | SP | + | TM | + | TP | ||
s.t. | |||||||||||||
FM | + | SM | + | TM | ≤ | ||||||||
FM | + | SM | ≤ | ||||||||||
FM | + | SM | + | TM | ≤ | ||||||||
FM | + | FP | ≥ | ||||||||||
SM | + | SP | ≥ | ||||||||||
TM | + | TP | ≥ | ||||||||||
FM, FP, SM, SP, TM, TP ≥ 0 |
If required, round your answers to the nearest whole number. If an amount is zero, enter "0".
Manufacture | Purchase | |
---|---|---|
Frames | ||
Supports | ||
Straps |
Department | Hours of production time used |
---|---|
Cutting | hours |
Milling | hours |
Shaping | hours |