The following information is known about a project:
a. Draw a network diagram
b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project
Activity | Activity Time (days) | Immediate Predecessor |
A | 12 | |
B | 9 | |
C | 10 | A |
D | 10 | A,B |
E | 24 | B |
F | 10 | A |
G | 35 | C |
H | 40 | D |
I | 15 | A |
J | 4 | E,G,H |
K | 6 | F,I,J |
the question is about project network......above images contains answer of that...
Get Answers For Free
Most questions answered within 1 hours.