Question

The following information is known about a project: a. Draw a network diagram b. Calculate the...

The following information is known about a project:

a. Draw a network diagram

b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project

Activity Activity Time (days) Immediate Predecessor
A 12
B 9
C 10 A
D 10 A,B
E 24 B
F 10 A
G 35 C
H 40 D
I 15 A
J 4 E,G,H
K 6 F,I,J

Homework Answers

Answer #1

the question is about project network......above images contains answer of that...

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Work with your group to practice the critical path method of scheduling Draw the network diagram...
Work with your group to practice the critical path method of scheduling Draw the network diagram using the SmartArt tool in any Microsoft Office application Follow the convention for drawing each node, allowing space for ES, EF, LS, LF and float Identify all the paths in the schedule Use the enumeration method to identify the critical path Make a forward pass to find the early schedule dates Make a backward pass to find the late schedule dates Define the float...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What...
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
The R&D Department is planning to bid on a large project for the development of a...
The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes.  The accompanying table shows the activities, times, and sequences required: Activity Immediate Predecessor Optimistic Most Likely Pessimistic A - 3 6 8 B A 2 4 4 C A 1 2 3 D C 6 7 8 E B,D 2 4 6 F B 6 10 14 G E, F 1 2 4 H F 3 6 9 I...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT