A work center at the Mechanical Lyold Company has 4 machines and each machine is operated 8.5 hours a day, 6 days a week. Last week, the work center operated for a total 158 hours and produced 140 hours of work.
b. The following three jobs (A, B & C) are scheduled for a work center. Determine the total time in standard hours required to execute the jobs at the work center.
Job A; order quantity= 150; run time per units = 0.5 hours and setup time is 2.2 hours. Job B, order quantity is = 220 units, run time is 0.15 hour/unit and setup time is 3.5 hours. Job C, order quantity= 250 units, run time is 0.12 hours/unit and setup time is 4.6 hours.