Question

Show both the network and the linear programming formulation for this assignment problem. ​ Task Person...

Show both the network and the linear programming formulation for this assignment problem. ​

Task

Person

A

B

C

D

1

9

5

4

2

2

12

6

3

5

3

11

6

5

7

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Linear Programming Formulation Project IE-311 Operation Research I Western Bank of Commerce and Industry (WBCI) is...
Linear Programming Formulation Project IE-311 Operation Research I Western Bank of Commerce and Industry (WBCI) is a busy bank that has requirements for between 10 and 18 tellers, depending on the time of the day. The afternoon time, from noon to 2 P.M., is usually heaviest. The table below indicates the workers needed at various hours that the bank is open: Time Period Number Required 9 A.M - 10 A.M 10 10 A.M. – 11 A.M. 12 11 A.M. –...
If a problem is referred to as a linear programming problem, what must be true? A)...
If a problem is referred to as a linear programming problem, what must be true? A) the objective function must be linear B) both the objective function and the constraints must be linear C) the constraints must be linear D) the decision variables must be linear Three essential elements of a linear programming formulation are the: A) decision variables, feasibility, constraints B) constraints, objective function, non-negativity C) decision variables, objective function, constraints D) objective function, constraints, solution When constraints identify...
A 6-node network with the following list of distances between various pairs of nodes: From Node...
A 6-node network with the following list of distances between various pairs of nodes: From Node To Node Distance 1 2 150 1 3 200 2 3 100 2 4 200 2 5 50 3 4 350 3 5 300 4 6 100 5 6 100 10a) Formulate finding the shortest route from node 1 to node 6 as a linear programming problem. 10b) Solve the problem on a linear programming software and show the total distance and the connections...
Consider the following linear programming formulation: Min      Z = X 1 + X 2 Subject to...
Consider the following linear programming formulation: Min      Z = X 1 + X 2 Subject to X 1 + X 2 ≥ 3 X 1 + X 2 ≥ 5 X 1, X 2 ≥ 0 Identify the feasible region in the graph below. Only one constraint will be shifted at a time. Which shift will produce an increase of the current feasible area? YOUR ANSWER CORRECT ANSWER X 1 + X 2 ≥ 3 shifts to X 1 +...
Consider the following linear programming problem. Maximize        6X1 + 4X2 Subject to:                     &nbs
Consider the following linear programming problem. Maximize        6X1 + 4X2 Subject to:                         X1 + 2X2 ≤ 16                         3X1 + 2X2 ≤ 24                         X1  ≥ 2                         X1, X2 ≥ 0 Use Excel Solver to find the optimal values of X1 and X2. In other words, your decision variables: a. (10, 0) b. (12, 2) c. (7, 5) d. (0, 10)
1. Consider the following linear programming problem formulated by a team of business analysts at the...
1. Consider the following linear programming problem formulated by a team of business analysts at the JORDANA Company Inc. Max 3A+4B s.t. -1A + 2B ≤ 8 Constraint 1 1A +2B ≤ 12 Constraint 2 2A + 1B ≤ 16 Constraint 3 (a) Show the feasible region using the geometric or graphical approach. (b) What are the optimal values of the decision variables? (c) Find the optimal solution to this optimization problem.
C++ PROGRAMMING Assignment: For this assignment, you will construct a program which is capable of taking...
C++ PROGRAMMING Assignment: For this assignment, you will construct a program which is capable of taking a user-given number, and adding up all of the numbers between 1 and the given number. So if someone inputs 12, it should add 1 + 2 + 3 + 4 + … 9 + 10 + 11 + 12, and return the answer. However, you’ll be using two different methods to do this. The first method should utilize either a for loop or...
               For the following linear programming problem, determine the optimal solution by the...
               For the following linear programming problem, determine the optimal solution by the graphical solution method                                                                                              Max   -x + 2y                                                                                                          s.t.   6x - 2y <= 3          ...
1.For the following linear programming problem Max 5X + 7Y s.t. 1X+ 1Y≤ 6 3X +1Y...
1.For the following linear programming problem Max 5X + 7Y s.t. 1X+ 1Y≤ 6 3X +1Y ≤ 12 X+ 2Y ≤ 10 X, Y ≥ 0 a)Write the problem in standard form. b)Solve the problem neatly using the graphical solution procedure(on paper). c)What are the values of the three slack variables at the optimal solution? d)Solve the problem with Microsoft Excel and attach your “own” printout.
You have been asked to sequence the following jobs. Task A must always be done before...
You have been asked to sequence the following jobs. Task A must always be done before Task B. Using Johnson's Rule, in what order will you do the jobs? Job Task A Task B A 3 6 B 7 6 C 5 2 D 5 8 E 4 7 F 9 3 G 1 4
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT