Month | Number of Cavities Filled | Total Cost |
January | 650 | $6,200 |
February | 500 | 5,750 |
March | 625 | 5,550 |
April | 425 | 5,550 |
May | 600 | 5,850 |
June | 450 | 5,150 |
July | 575 | 6,150 |
August | 700 | 6,100 |
September | 350 | 5,050 |
Required:
1. Use the high-low method to estimate total fixed cost
and variable cost per cavity filled. (Round your answers to
2 decimal places.)
Fixed Cost | |
Variable Cost per Unit |
2. Using these estimates, calculate Mountain’s
total cost for filling 400 cavities.
Estimated Total Cost :
Variable cost per cavity = Change in cost/change in activity
= (6100-5050)/(700-350)
Variable cost per cavity = 3 per cavity
Fixed cost = Total cost-variable cost
= 6100-(700*3)
FIxed cost = 4000
Estimated total cost on 400 cavities = (400*3)+4000 = 5200