Question

Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech...

Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building:

Title insurance $ 26,000
Legal fees for drawing the contract 5,000
Pro-rated property taxes for the period after acquisition 46,000
State transfer fees 5,000


An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent $92,000 to construct a parking lot and $50,000 for landscaping.

Required:
2. Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $350,000 and the salvaged materials were sold for $6,000. In addition, Samtech spent $89,000 clearing and grading the land in preparation for the construction of a new building.

Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $350,000 and the salvaged materials were sold for $6,000. In addition, Samtech spent $89,000 clearing and grading the land in preparation for the construction of a new building. (Enter your answers in whole dollars.)

Assets Initial Valuation
Land
Building
Land improvements

Homework Answers

Answer #1
ans 2
Total cost
Purchase price $4,000,000
Title insurance 26,000
Legal fees for drawing the contract 5,000
State transfer fees 5,000
Demolition cost 350,000
Less: salvage value -6,000
Clearing and grading of land 89,000
Total cost $4,469,000
pro rated propety taxes are not part of acquisition
Total cost is cost of land as building is demolished) $4,469,000
land improvement=Parking lot+landscaping (92000+50000) 142000
building (as this is demolished hence $0) $0
answer
Assets Initial Valuation
Land $4,469,000
Building $0
Land improvements 142000
If any doubt please comment
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 35,000 Legal fees for drawing the contract 9,500 Pro-rated property taxes for the period after acquisition 55,000 State transfer fees 5,900 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.6 and $1.2 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title Insurance $23,000 Legal fees for drawing the contacts $8,500 Pro-rated property taxes for the period after acquisition $43,000 State transfer fees $4,700 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $2 million, respectively. Shortly after acquisition, Samtech spent $89,000...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 36,000 Legal fees for drawing the contract 10,000 Pro-rated property taxes for the period after acquisition 56,000 State transfer fees 6,000 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $1 million, respectively. Shortly after acquisition, Samtech spent...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $1 million, respectively. Shortly after acquisition, Samtech spent $83,000 to construct a parking lot and $41,000 for landscaping. Required: 1. Determine the initial valuation of each asset Samtech acquired in these transactions. 2. Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $260,000 and the salvaged materials were sold for $6,500. In...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.5 and $1.5 million, respectively. Shortly after acquisition, Samtech spent $97,000 to construct a parking lot and $55,000 for landscaping. Required: 1. Determine the initial valuation of each asset Samtech acquired in these transactions. 2. Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $400,000 and the salvaged materials were sold for $8,500. In...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2018) 4,100 Construction costs 610,000 Interest on...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
Fullerton Waste Management purchased land and a warehouse for $640,000. In addition to the purchase price,...
Fullerton Waste Management purchased land and a warehouse for $640,000. In addition to the purchase price, Fullerton made the following expenditures related to the acquisition: broker’s commission, $34,000; title insurance, $5,000; miscellaneous closing costs, $8,000. The warehouse was immediately demolished at a cost of $22,000 in anticipation of the building of a new warehouse. Determine the amounts Fullerton should capitalize as the cost of the land and the building. Capitalized cost of land Capitalized cost of building
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT