Question

A purchasing manager had to purchase a greater quantity of material than was budgeted for production...

A purchasing manager had to purchase a greater quantity of material than was budgeted for production and paid the higher price for the purchase. Which of the following variances may be affected?
a.) material price variance
b.) both price and quanity variance
c.) material quantity variance
d.) neither varjances will be affected

Homework Answers

Answer #1

Answer:

Option b: Both price & quantity variance

Explanation:

Material price variance = (Standard Price - Actual price) * Actual Quantity

So, when actual price spent is more than the standard price, the material price variance would be negative.

Material quantity variance = (Standard quantity - Actual Quantity) * Standard Price

So, when the actual quantity purchased is more than the quantity budgeted, the material quantity/usage variance would be negative.

In the given question, the greater quantity was purchased and at a higher price than budgeted, therefore, both the variances i.e. material price variance and material quantity variance would be affected.

Hence,

Option 'b' is correct and rest all are incorrect.

In case of any doubt, please feel free to comment.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A favorable material price variance indicates that: actual quantity is less than the standard quantity B....
A favorable material price variance indicates that: actual quantity is less than the standard quantity B. The actual quantity is greater than the standard quantity c. actual price is less than the standard price actual price is greater than the standard price
Which of the following statements about direct material variances are likely to be true? Differences between...
Which of the following statements about direct material variances are likely to be true? Differences between the actual production level and budgeted (expected) production level is NOT a reason why direct materials quantity (or efficiency) variances arise. A direct materials quantity (or efficiency) variance can arise due to factors outside the production manager's control A direct materials quantity (or efficiency) variance will arise if the organisation manages to negotiate a better price for its materials compared to what it had...
QUESTION 5 (20 Marks) Information: A standard quantity of 2kg of material X at a standard...
QUESTION 5 Information: A standard quantity of 2kg of material X at a standard price of R4 per kg is allowed for the production of one unit of product Messi. The cost figures for the first quarter of 2020 showed that 4 400 kg of material X was purchased at R4.10 per kg. 2000 units of product Messi were produced using 4 200 kg of material X. Required: In respect of material, calculate and briefly comment on the following variances:...
1) Which budget is the starting point in preparing financial budgets? Group of answer choices A)...
1) Which budget is the starting point in preparing financial budgets? Group of answer choices A) the budgeted balance sheet B) the capital expense budget C) the budgeted income statement D) the cash receipts budget 2) The direct materials budget is prepared using which budget's information? Group of answer choices A) raw materials budget B) cash receipts budget C) cash payments budget D) production budget 3. Which of the following includes only financial budgets? Group of answer choices A) budgeted...
Which of the following is not true of variances? A. Material spending (total) variance = Price...
Which of the following is not true of variances? A. Material spending (total) variance = Price variance + Quantity variance. B. Spending (total) variance = Actual cost  – Standard cost C. If a cost variance is negative, it is favorable. D. (Price variance) X (Quantity variance) < 0
The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total...
The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total cost of $1,677,000 ($13 per board foot). Original production had been budgeted for 22,000 units with a standard material quantity of 5.7 board feet per unit and a standard price of $12 per board foot. Actual production was 23,500 units. 1.   Compute the material price variance. a. 0 b. 129,000U c. 59,400F d. 59,400U 2. Compute the material quantity variance. a. 63,000F b. 63,000U...
1. Russell, Inc. has forecast purchases on account to be $315,000 in March, $372,000 in April,...
1. Russell, Inc. has forecast purchases on account to be $315,000 in March, $372,000 in April, $424,000 in May, and $494,000 in June. Sixty five percent of purchases are paid for in the month of purchase, the remaining 35% are paid in the following month. What are budgeted cash payments for April? Multiple Choice $352,050 $259,050 $385,050 $126,050 2. Who would typically be responsible for the direct materials quantity variance? Multiple Choice The chief financial officer The production manager The...
5. In early 2012, Duncan Manufacturing Inc. had budgeted for the production and sale of 20,000...
5. In early 2012, Duncan Manufacturing Inc. had budgeted for the production and sale of 20,000 units at a sales price of $25 per unit. The following information is available regarding the standard cost for each unit: Direct materials: $6.00 (3 pounds at $2.00 per lb) Direct labor: $3.50 (10 minutes of assembly at $.35 per minute) Actual results for 2012 were determined to be as follows: Number of units produced and sold: 18,000 units Sales revenue: $477,000 ($26.5 per...
Direct Materials Variances The following data relate to the direct materials cost for the production of...
Direct Materials Variances The following data relate to the direct materials cost for the production of 2,100 automobile tires: Actual: 60,300 lbs. at $1.75 $105,525 Standard: 58,500 lbs. at $1.8 $105,300 a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Price variance $ Quantity variance $ Total direct materials cost variance $...
Direct Materials Variances The following data relate to the direct materials cost for the production of...
Direct Materials Variances The following data relate to the direct materials cost for the production of 1,800 automobile tires: Actual: 52,000 lbs. at $1.9 $98,800 Standard: 50,400 lbs. at $1.95 $98,280 a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Price variance $ Quantity variance $ Total direct materials cost variance $...