Marbles Company has the following information available regarding its materials:
Managers expected to pay $5 per kilogram, but ended up paying $6 per kilogram. Each unit produced should take 2 kilograms; actual total usage was 2,100 kilograms. Finally, the company planned to produce 1,000 units, but only produced 950.
Calculate the materials efficiency variance.
$2,100 (unfavorable)
$0
$1,000 (unfavorable)
$1,400 (unfavorable)
Marbles Company has the following information available regarding its materials:
Managers expected to pay $5 per kilogram, but ended up paying $6 per kilogram. Each unit produced should take 2 kilograms; actual total usage was 2,100 kilograms. Finally, the company planned to produce 1,000 units, but only produced 950.
Calculate the materials activity variance.
$2,500 (unfavorable)
$500 (unfavorable)
$500 (favorable)
$2,500 (favorable)
1.
Correct answer for first question is option c = $ 1,000 unfavourable.
Working :
Material efficiency variance :
= ( standard quantity for actual output - actual quantity * standard cost
= { ( 950 unit * 2 kg per unit) - 2,100 kg } * $ 5 per kg
= ( 1,900 kg - 2,100 kg ) * $ 5 per kg
= - 200 kg * $ 5 per kg
= - $ 1,000
~~~~
2.
Correct answer for second question is option c = $ 500 favourable.
Working :
Material activity variance :
=( budgeted production units - actual units produced ) * standard price per unit
= ( 1000 unit - 950 units ) * ( 2 kg per unit * $ 5 per kg)
= 50 units * $ 10 per unit
= $ 500
~~~~ please upvote. Thanx.
Get Answers For Free
Most questions answered within 1 hours.