Budget Performance Reports for Cost Centers
Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow:
Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 |
||||||||
Plant | Actual | Budget | Over Budget | Under Budget | ||||
Eastern Region | $543,100 | $543,100 | $0 | |||||
Central Region | 391,000 | 387,100 | $3,900 | |||||
Western Region | (g) | (h) | (i) | |||||
$(j) | $(k) | $(l) | $2,740 |
Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 |
||||||||
Department | Actual | Budget | Over Budget | Under Budget | ||||
Chip Fabrication | $(a) | $(b) | $(c) | |||||
Electronic Assembly | 84,810 | 85,910 | 1,100 | |||||
Final Assembly | 135,700 | 134,610 | $1,090 | |||||
$(d) | $(e) | $(f) | $3,830 |
Garland Company Budget Performance Report—Supervisor, Chip Fabrication For the Month Ended November 30 |
||||||||
Cost | Actual | Budget | Over Budget | Under Budget | ||||
Factory wages | $24,020 | $25,700 | $1,680 | |||||
Materials | 59,460 | 59,040 | $420 | |||||
Power and light | 3,460 | 4,120 | 660 | |||||
Maintenance | 8,500 | 9,310 | 810 | |||||
$95,440 | $98,170 | $420 | $3,150 |
a. Complete the budget performance reports by determining the correct amounts for the lettered spaces (a-l) as marked above.
a. $ | g. $ |
b. $ | h. $ |
c. $ | i. $ |
d. $ | j. $ |
e. $ | k. $ |
f. $ | l. $ |
b. The budget for the Chip Fabrication Department indicates that the budget overrun was caused by a combination of budget in factory wages, power and light, and maintenance that exceeded a budget in materials.
(a)
Cost | Actual | Budget | Over Budget | Under budget |
Factory wages | 24020 | 25700 | 1680 | |
Materials | 59460 | 59040 | 420 | |
Power and light | 3460 | 4120 | 660 | |
Maintenance | 8500 | 9310 | 810 | |
95,440 | 98,170 | 420 | 3,150 |
Department | Actual | Budget | Over budget | Under budget |
Chip fabrication | (a) 95,440 | (b) 98,170 | (c) 2,730 | |
Electronic assembly | 84,810 | 85,910 | 1,100 | |
Final assembly | 135,700 | 134,610 | 1,090 | |
(d) 315,950 | (e) 318,690 | (f) 1,090 | 3,830 |
Plant | Actual | Budget | Over budget | Under budget |
Eastern region | 543,100 | 543,100 | ||
Central region | 391,000 | 387,100 | 3,900 | |
Western region | (g) 315,950 | (h) 318,690 | (i) 2,740 | |
(j) 1,250,050 | (k) 1,248,890 | (l) 3,900 | 2,740 |
(b) The budget for the Chip Fabrication Department indicates that the budget overrun was caused by a combination of budget overrun in factory wages, power and light, and maintenance that exceeded a budget surplus balance in materials.