Question

1.A process cost system and a job order cost system both use a predetermined overhead rate...

1.A process cost system and a job order cost system both use a predetermined overhead rate to apply estimated manufacturing overhead costs to work in process.

true or false

2. Under job-order costing, the actual direct material, actual direct labor, and estimated overhead costs are recorded on the job cost sheet.

true or false

3. In a job-order cost system, the inventory accounts generally are maintained on a perpetual basis.

true or false

4. Process costing is used for products produced in mass quantities through a continuous process that provides similar inputs to each unit produced.

true or false

Homework Answers

Answer #1

Answer 1: True.

Explanation: Both process and job costing use a predetermined overhead rate to apply estimated manufacturing overhead costs.

Answer 2: False.

Explanation: Under job-order costing, the actual direct material, actual direct labor, and applied manufacturing overhead costs are recorded on the job cost sheet.

Answer 3. True.

Explanation: Being a cost accounting system , job -order cost system maintains the inventory record as per perpetual inventory system.

Answer 4 . True.

Explanation: Under process costing mass quantities of product are produced through a continuous process that uses similar amount of material, labor & overhead to each unit produced

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $66,000 and 22,000 hours, respectively. In June, Job #461 was completed. Materials costs on the job totaled $4,923 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked 23,975 direct...
A job-order costing system that relies on normal costing will: Multiple Choice Assign actual direct materials...
A job-order costing system that relies on normal costing will: Multiple Choice Assign actual direct materials and direct labor costs to jobs. Apply overhead cost to jobs by multiplying an actual overhead rate by the estimated amount of the allocation base incurred by the jobs. Apply overhead cost to jobs by multiplying an actual overhead rate by the actual amount of the allocation base incurred by the jobs. Apply overhead cost to jobs by multiplying a predetermined overhead rate by...
A job-order costing system that relies on normal costing will: Multiple Choice Assign actual direct materials...
A job-order costing system that relies on normal costing will: Multiple Choice Assign actual direct materials and direct labor costs to jobs. Apply overhead cost to jobs by multiplying an actual overhead rate by the estimated amount of the allocation base incurred by the jobs. Apply overhead cost to jobs by multiplying an actual overhead rate by the actual amount of the allocation base incurred by the jobs. Apply overhead cost to jobs by multiplying a predetermined overhead rate by...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $678,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 30 Total direct labor-hours 300 Direct materials $ 1,350 Direct labor cost $ 11,400...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct labor-hours. At the start of the year, MOH cost was estimated at $100,000 for the year. And, the number of DL hours to be used during the year was estimated at 40,000. In September, Job #274 was completed at a cost of $5,000 in direct materials and $2,400 in direct labor. The labor rate is $6 per hour. By the end of the year,...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,000 Total fixed manufacturing overhead cost $ 252,000 Variable manufacturing overhead per machine-hour $ 2.10 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 675 Direct labor cost $ 1,050 The estimated total...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours      30,500 Total fixed manufacturing overhead cost   $   610,000 Variable manufacturing overhead per machine-hour   $   6.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job      10 Total machine-hours      30 Direct materials   $   690 Direct labor cost   $   1,370...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 26,000 direct labor-hours, total fixed manufacturing overhead cost of $195,000, and a variable manufacturing overhead rate of $2.10 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 400...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,500 Total fixed manufacturing overhead cost $455,000 Variable manufacturing overhead per machine-hour $ 5.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 710 Direct labor cost $1,420 If the company marks...