Question

The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...

The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows:

Standard Costs
Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour
Variable overhead 3 hours per unit @ $2.06 per hour

Actual Costs
    Total variable cost, $18,000
    Total fixed cost, $7,900

The fixed factory overhead volume variance is

a.$720 unfavorable

b.$0

c.$576 unfavorable

d.$576 favorable

The following data are given for Bahia Company:

Budgeted production 1,064 units
Actual production   919 units
Materials:
    Standard price per pound $1.938
    Standard pounds per completed unit 10
     Actual pounds purchased and used in production 8,914
     Actual price paid for materials $18,274
Labor:
    Standard hourly labor rate $14.80 per hour
    Standard hours allowed per completed unit 4.9
    Actual labor hours worked 4,732.85
    Actual total labor costs $72,176
Overhead:
    Actual and budgeted fixed overhead $1,108,000
    Standard variable overhead rate $24.00 per standard labor hour
    Actual variable overhead costs $132,520
Overhead is applied on standard labor hours.

The variable factory overhead controllable variance is

a.$150,996.24 unfavorable

b.$150,996.24 favorable

c.$24,445.60 unfavorable

d.$24,445.60 favorable

Which of the following conditions normally would not indicate that standard costs should be revised?

a.Actual costs differed from standard costs for the preceding week.

b.The average price of raw materials increased from $4.68 per pound to $4.82 per pound.

c.The Engineering Department has revised product specifications in responding to customer suggestions.

d.The company has signed a new union contract that increases the factory wages on average by $3.50 an hour.

Standards that represent levels of operation that can be attained with reasonable effort are called

a.normal standards

b.theoretical standards

c.variable standards

d.ideal standards

Homework Answers

Answer #1

The fixed factory overhead volume variance is $720 U

Reason:- Fixed factory overhead volume variance = Budget Fixed cost allocation - Budgeted rate x Actual Hours = ($0.72 x 3 x 3,000) - ($0.72 x 10,000) = $720 U

The variable factory overhead controllable variance is

Reason:- ariable factory overhead controllable variance = Actual overhead expense - (budgeted overhead per unit x standard number of units) = $132,520 - ($24 x 4.9 hrs x 919 units) = $24,445.60 U

Which of the following conditions normally would not indicate that standard costs should be revised?

c.The Engineering Department has revised product specifications in responding to customer suggestions.

Standards that represent levels of operation that can be attained with reasonable effort are called

a.Normal Standards

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $2.01 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $7,900 The total factory overhead cost variance is a.$-90 unfavorable b.$610 unfavorable c.$1,310 favorable d.$610 favorable
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $1.99 per hour Actual Costs     Total variable cost, $17,900     Total fixed cost, $8,200 The total factory overhead cost variance is a.$-10 unfavorable b.$690 unfavorable c.$1,390 favorable d.$690 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.75 per hour Variable overhead 3 hours per unit @ $1.97 per hour Actual Costs     Total variable cost, $17,900     Total fixed cost, $8,000 The amount of the total factory overhead cost variance is a.$5,000 favorable b.$5,000 unfavorable c.$3,125 unfavorable d.$6,875 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.71 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,000 The fixed factory overhead volume variance is a.$0 b.$909 unfavorable c.$1,136 unfavorable d.$909 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.78 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $17,800     Total fixed cost, $8,100 The variable factory overhead controllable variance is a.$1,756 favorable b.$1,756 unfavorable c.$1,405 favorable d.$0
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.77 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $18,100     Total fixed cost, $8,200 The amount of the variable factory overhead controllable variance is a.$2,056 favorable b.$0 c.$2,056 unfavorable d.$1,645 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.72 per hour Variable overhead 3 hours per unit at $1.99 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $7,900 The total factory overhead cost variance is
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.61 Actual Costs Direct materials 2,600 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is $426 favorable $426 unfavorable $1,066 favorable $1,066 unfavorable Q2: The standard costs and actual costs for direct materials for the manufacture of 2,650 actual units of...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 994 units were actually produced. Labor standards were 7.6 hours per completed unit at a standard rate of $12.86 per hour. The direct labor rate variance is a.$6,881.72 unfavorable b.$6,881.72 favorable c.$5,577.18 unfavorable d.$5,577.18 favorable 21. Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.08 per hour. Original...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 6,800 units of product were as follows: Standard Costs Actual Costs Direct materials 8,800 lb. at $4.90 8,700...