During April, Crowley Company produced 1,200 units, incurred 3,700 labor hours and had a labor efficiency variance of $2,000U. If the standard unit consumes 3 labor hours, and if the actual labor cost was $78,000, what is the labor rate variance? Enter a favorable variance as a positive number and an unfavorable variance as a negative number.