Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...

Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:

Days

Wait time 15.9

Inspection time 0.6

Process time 3.8

Move time 0.3

Queue time 3.2

Required:

a. Compute the throughput time. (Round your answer to 1 decimal places.)

b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.)

c. What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage.)

d. Compute the delivery cycle time. (Round your answer to 1 decimal place.)

Homework Answers

Answer #1

Ans:

1
Throughput time = Inspection time+Process time +Move time +Queue time
Throughput time = 0.6+3.8+0.30+3.2= 7.6 days
2
Manufacturing cycle efficiency = Process time ÷ Throughput time
Manufacturing cycle efficiency = 3.8/7.6= 0.50
3
Percentage of the production time in non-value-added activities = 1-0.50 = 50%
4
Delivery cycle time = Wait time + Throughput time
Delivery cycle time = 15.9+7.6= 23.5 days


Hope This Helped ! Let Me Know In Case of Any Queries.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.3 Inspection time 0.2 Process time 1.4 Move time 1.3 Queue time 2.5 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 13.2 Inspection time 0.7 Process time 1.60 Move time 0.6 Queue time 2.2 Required: a. Compute the throughput time.(Enter your answer rounded to 1 decimal...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 15.9 days Process time 2.7 days Move time 1.2 days Queue time 3.5 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 16.2 days Process time 3.2 days Move time 1.5 days Queue time 4.0 days Required: 1. Compute the throughput time. (Round your answer to...
Astro Clothing Company wants to reduce the length of time between a customer placing an online...
Astro Clothing Company wants to reduce the length of time between a customer placing an online order and when that order is actually shipped. Astro Clothing proivdes the following data from operations: Inspection time 0.6 days Wait time (from order to start of production) 15.5 days Process time 3.3 days Move time 1.0 days Queue time 3.8 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the...
Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln,...
Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 15.9 days Process time 2.9 days Move time 0.8 days Queue time 3.9 days Required:...
Exercise 12-3 Measures of Internal Business Process Performance [LO12-3] Management of Mittel Rhein AG of Köln,...
Exercise 12-3 Measures of Internal Business Process Performance [LO12-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 day Wait time (from order tostart of production) 16.4 days Process time 3.2 days Move time 0.5 day Queue time 3.9 days Required: 1.Compute...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:   Inspection time 0.6 days   Wait time (from order to start of production) 16.8 days   Process time 3.5 days   Move time 0.6 days   Queue time 3.9 days Required: 1. Compute the throughput time. (Round your answer to...
22. Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average...
22. Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.50, its average move time is 0.6 day, and its average queue time is 2.2 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:   Inspection time 0.4 days   Wait time (from order to start of production) 17.0 days   Process time 3.1 days   Move time 1.1 days   Queue time 4.2 days Required: 1. Compute the throughput time. (Round your answer to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT