Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available:
Quantity of direct labor used | 540 hrs. |
Actual rate for direct labor | $14.20 per hr. |
Bicycles completed in October | 250 bicycles |
Standard direct labor per bicycle | 2 hrs. |
Standard rate for direct labor | $14.50 per hr. |
a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct Labor Rate Variance | $ | |
Direct Labor Time Variance | $ | |
Total Direct Labor Cost Variance | $ |
b. How much direct labor should be debited to
Work in Process?
$