Question

If McKamie Hobbies, Inc. has a safety stock of 70 units and the average weekly demand...

If McKamie Hobbies, Inc. has a safety stock of 70 units and the average weekly demand is 14 units, how many days can be covered if the shipment from the supplier is delayed ?

5 days

35.days

42 days

70 days

Homework Answers

Answer #1

Safety Stock = 70 Units

Average Weekly Demand = 14 Units

Number of weeks that can be covered if the shipment from the supplier is delayed = Safety Stock / Average Weekly Demand

Number of weeks that can be covered if the shipment from the supplier is delayed = 70 Units / 14 Units = 5 Weeks

Number of days that can be covered if the shipment from the supplier is delayed = 7 Days * Number of weeks that can be covered if the shipment is delayed

Number of days that can be covered if the shipment from the supplier is delayed = 7 Days * 5 Weeks = 35 Days

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day and a weekly standard deviation of 125. The product’s lead time is 20 days. Currently, the reorder point for this product is 8,200. The company work 5 days per week. If the company would like to have a service level of 95% for this product then A. it must decrease its safety stock by approximately 412 units. B. it must decrease its safety stock...
Use the information in the following table to answer the questions below: Demand 100 units per...
Use the information in the following table to answer the questions below: Demand 100 units per week Standard deviation of weekly demand 10 units Average lead time 10 days Standard deviation of the lead time 5 days Cycle service level 70 % Considering a continuous review system, Find the standard deviation of demand during the lead time. Find the safety stock. What is the reorder point?
Ray's Satellite Emporium wishes to determine the best order size for its best-selling satellite dish. Ray...
Ray's Satellite Emporium wishes to determine the best order size for its best-selling satellite dish. Ray has estimated that weekly demand for this model to be 25 units with a standard deviation of 5 units. His cost to carry one unit is $50 per year and the cost of placing an order with his supplier is $25. He's open 52 weeks a year. Assume weekly demand is normally distributed. (4 pts each) a. What is Ray’s economic order quantity in...
MNO has an average annual demand for red, medium polo shirts of 100,000 units. The cost...
MNO has an average annual demand for red, medium polo shirts of 100,000 units. The cost of placing an order is $500 and the cost of carrying one unit in inventory for one year is $20. Required: a. Use the economic-order-quantity model to determine the optimal order size. b. Determine the reorder point assuming a lead time of 12 days and the store is open 250 days in the year. c. Determine the safety stock required to prevent stockouts assuming...
Bed Bath & Microwaves has problems with its best-selling microwave—the SonicMicrowave. Hank, the owner, tells you...
Bed Bath & Microwaves has problems with its best-selling microwave—the SonicMicrowave. Hank, the owner, tells you that he always seems to have too many or too few of the SonicMicrowave. He has hired you to help determine how much and when to order. At the same time, the company is considering quotes from 2 different suppliers, and you will help compare suppliers. You estimated the following information from the detailed records that Hank kept on the microwave. You calculated the...
The annual demand for a product is 15,900 units. The weekly demand is 306 units with...
The annual demand for a product is 15,900 units. The weekly demand is 306 units with a standard deviation of 80 units. The cost to place an order is $33.50, and the time from ordering to receipt is eight weeks. The annual inventory carrying cost is $0.10 per unit. a. Find the reorder point necessary to provide a 99 percent service probability. (Use Excel's NORMSINV() function to find the correct critical value for the given α-level. Round "z" value to...
An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a...
An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a maximum daily demand of 12 units. The economic order quantity is 200 units. Without safety stocks, the reorder point is 50 units. Safety stocks are set at 94 units. Required: a. Determine the reorder point with safety stocks. b. Determine the maximum inventory level. c. Determine the average lead time. d. Determine the maximum lead time
Marshall, Inc., produces three products but weekly demand for the three products exceed the available amount...
Marshall, Inc., produces three products but weekly demand for the three products exceed the available amount of machine time. Following is information about each product:    Product A Product B Product C Contribution margin per unit $ 300 $ 400 $ 150 Machine hours per unit 3 2 0.50 Weekly demand (units) 100 300 800 (a.) Determine how many units each of Product A, Product B, and Product C that Marshall, Inc., should produce each week assuming 1,000 hours of...
A product with an annual demand of 1100 units has Co = $24.5 and Ch =...
A product with an annual demand of 1100 units has Co = $24.5 and Ch = $7. The demand exhibits some variability such that the lead-time demand follows a normal probability distribution with µ = 30 and σ = 6. What is the recommended order quantity? If required, round your answer to two decimal places. Q* = What are the reorder point and safety stock if the firm desires at most a 3% probability of stock-out on any given order...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT