Question

What cost hierarchy does Packaging and Shipping activity, Receiving and production activity, and Engineering activity fall...

What cost hierarchy does Packaging and Shipping activity, Receiving and production activity, and Engineering activity fall under?

Homework Answers

Answer #1

Generally cost hierarchy categories in to four Catenaries.

Unit level

Batch level

Product level

Facility level

Activity

Packaging and Shipping activity

Batch level

Packaging and Delivery Cost incurred On every group of product wise.

Receiving and production activity

Batch level

This Cost Incurred per Batch wise. Production and Inventory Control activity.

Engineering activity

Product level

This activity Support entire Product wise, such as Change in Product design, Engineering work etc.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
list the general levels of cost hierarchy in activity based costing
list the general levels of cost hierarchy in activity based costing
7.1)   In receiving DAAs from the pharmacy what checks should be made to packaging and by whom?
7.1)   In receiving DAAs from the pharmacy what checks should be made to packaging and by whom?
Activity Cost Pools, Activity Rates, and Product Costs using Activity-Based Costing Caldwell Home Appliances Inc. is...
Activity Cost Pools, Activity Rates, and Product Costs using Activity-Based Costing Caldwell Home Appliances Inc. is estimating the activity cost associated with producing ovens and refrigerators. The indirect labor can be traced into four separate activity pools, based on time records provided by the employees. The budgeted activity cost and activity-base information are provided as follows: Activity Activity Pool Cost Activity Base Procurement $144,480 Number of purchase orders Scheduling 6,300 Number of production orders Materials handling 30,420 Number of moves...
What is the value of the variable shipping if cost = 50 and country = "Canada"?...
What is the value of the variable shipping if cost = 50 and country = "Canada"? if (cost < 50 && country == "Canada") shipping = 6.00; if (cost < 100 && cost > 49 && country == "Canada") shipping = 9.00; else shipping = 12.00; A. 12.00 B. cannot tell since the else clause does not specify the conditions C. 9.00 D. 6.00
What is the hierarchy rule in crime-reporting programs? What purpose does it serve?
What is the hierarchy rule in crime-reporting programs? What purpose does it serve?
Questions: 1. What do we mean by cost behavior? 2. When activity increases, does the unit...
Questions: 1. What do we mean by cost behavior? 2. When activity increases, does the unit variable cost increase, decrease or remain the same? 3. When activity decreases, does the unit fixed cost increase, decrease or remain the same? 4. When activity decreases, does total variable cost increase, decrease or remain the same? 5. When activity increases, does total fixed cost increase, decrease or remain the same? 6. Define the following: a. Gross margin b. Contribution margin 7. What are...
What is the physical significance of the "activity coefficient" in chemical engineering? (as it relates to...
What is the physical significance of the "activity coefficient" in chemical engineering? (as it relates to components in a mixture...)
Answer A-C using info Equivalent units of production (EUP)- weighted average method (Forming and Packaging cost...
Answer A-C using info Equivalent units of production (EUP)- weighted average method (Forming and Packaging cost categories) Units % Forming Costs EUP- Forming % Packaging EUP- Packaging Units completed and transferred out 22,700 100% 22,700 100% 22,700 Ending work in process - units 1,960 65% 1,274 65% 1,274 Total units 24,660 23,974 23,974 Cost per equivalent unit of production Forming Packaging Costs of beginning work in process 400,000 200,000 Costs incurred this period 2,497,000 579,720 Total costs Costs 2,897,000 Costs...
Activity-Based Determining the cost of a product, which consist of direct materials, direct labor, and factory...
Activity-Based Determining the cost of a product, which consist of direct materials, direct labor, and factory overhead.Product Costing Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Activity Cost Pool Production $259,200 Changing the characteristics of a machine...
Identifying Activity Bases in an Activity-Based Cost System Comfort Foods Inc. uses activity-based costing to determine...
Identifying Activity Bases in an Activity-Based Cost System Comfort Foods Inc. uses activity-based costing to determine product costs. For each activity listed in the left column, select an appropriate activity base from the right column. You may use items in the dropdown list more than once or not at all. Activity Activity Base Cafeteria Customer return processing Electric power Human resources Inventory control Invoice and collecting Machine depreciation Materials handling Order shipping Payroll Performance reports Production control Production setup Purchasing...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT