Question

Question 1 Harbour Inc. collected the following data for the first six months of the year...

Question 1

Harbour Inc. collected the following data for the first six months of the year concerning its overhead costs and machine hours used.

Month

Overhead Costs ($)

Machine Hours

Jan

$62,000

400

Feb

52,000

320

Mar

64,000

395

Apr

58,000

350

May

57,000

350

June

54,000

325

Required -

a)            Harbour suspects that machine hours are driving overhead costs. Use the high-low method to calculate the:

i.             variable cost per machine hour;

ii.                monthly fixed cost.

b)           Harbour predicts that 375 machine hours will be used in July. Calculate the estimated overhead cost for July.

c)            Why is the high-low method inferior to the regression estimation method (provide 1 reason only)?

Homework Answers

Answer #1

Using High Low Method

Variable Cost Per Unit

=Highest Activity Cost - Lowest Activity Cost

Highest Activity Unit - Lowest Activity Unit

So Variable Cost per machine hour

= 62000-52000

400-320

= 125

Here 62000 is taken as highest instead of 64000 because overhead cost is driven by machine hours and maximum machine hours worked are 400 so overhead cost corresponding to highest and lowest machine hours will be taken.

a)

(i)So Variable cost per machine hour = $125

(ii) Monthly Fixed Cost = 62000 - (400*125) = $12000

b) Estimated Overhead Cost = 12000 + (375*125) = $58875

c) The high low method is inferior to regression analysis as it gives unreliable data as it only considers two extreme activity levels which may not be even representing the whole cost data.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Machine Master, Inc. had the following data regarding monthly power costs: Month Machine hours Power cost...
Machine Master, Inc. had the following data regarding monthly power costs: Month Machine hours Power cost Jan 300 $650 Feb 600 720 Mar 400 685 Apr 200 640 May 350 675 Use the high-low method, estimate the cost formula regarding monthly power costs Assume that management expects 500 machine hours in May. Calculate May’s power cost using machine hours as the basis for prediction.
Dundar Mifflin makes electronic products for the RCMP. The following data is for the first six...
Dundar Mifflin makes electronic products for the RCMP. The following data is for the first six months: Direct Labor Hours Manufacturing Overhead January 45,000 $295,000 February 65,000 $309,000 March 57,000 $323,000 April 58,000 $320,000 May 25,000 $181,000 June 29,000 $162,500 Required: 1. Use the high-low method to estimate the cost formula 2. Estimate the total overhead cost at an activity level of 40,000 machine hours, using the separate estimates you obtained for its components.
Johanson Company has provided the following data for the first five months of the year: Machine...
Johanson Company has provided the following data for the first five months of the year: Machine Hours Lubrication Cost January 120 $750 February 160 $800 March 200 $870 April 150 $790 May 170 $840 Using the High Low Method, compute the expected cost at 140 Machine Hours.
The controller of Norton Industries has collected the following monthly expense data for use in analyzing...
The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,930 350 February 3,230 400 March 3,830 550 April 4,730 640 May 3,430 550 June 5,840 750 Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g. 12.250.) Determine the fixed cost components using the high-low method. (Round answer to 0 decimal places...
Audio Zone Co. needs to prepare pro forma financial statements for the next fiscal year. To...
Audio Zone Co. needs to prepare pro forma financial statements for the next fiscal year. To do so, the company must forecast its total overhead cost. The actual machine hours and total overhead cost are presented below for the past six months. Month Total Overhead Machine Hours Jan. $ 6,320 1,990 Feb. 6,680 2,100 Mar. 6,020 1,750 Apr. 5,590 1,600 May 6,060 1,870 June 6,370 2,020 Using the high-low method, total monthly fixed overhead cost is calculated to be: $2,102....
The controller of Crane Industries has collected the following monthly expense data for use in analyzing...
The controller of Crane Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,590 330 February 2,890 380 March 3,490 530 April 4,390 660 May 3,090 530 June 4,790 730 (a1) Determine the variable cost components using the high-low method. (Round answer to 2 decimal places e.g. 2.25.) Variable cost per machine hour $enter the variable cost components using the high-low method rounded...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 217,820 May 38,000 $ 190,420 June 58,000 $ 245,220 July 68,000 $ 272,620 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 70,000 Maintenance (mixed) 63,420 Total overhead cost $ 190,420 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 199,940 May 38,000 $ 172,640 June 58,000 $ 227,240 July 68,000 $ 254,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 54,000 Maintenance (mixed) 61,640 Total overhead cost $ 172,640 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 198,260 May 42,000 $ 172,460 June 62,000 $ 224,060 July 72,000 $ 249,860 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 49,000 Maintenance (mixed) 64,660 Total overhead cost $ 172,460 Nova Company’s...
Cullumber Corp. has collected the following data concerning its maintenance costs for the past 6 months....
Cullumber Corp. has collected the following data concerning its maintenance costs for the past 6 months. Units Produced Total Cost July 20,190 $44,085 August 35,904 53,856 September 40,392 61,710 October 24,684 47,358 November 44,880 83,589 December 42,636 69,564 (a1) Compute the variable cost per unit using the high-low method. (Round answer to 2 decimal places, e.g. 2.25.) Variable cost per unit    (a2) Compute the fixed cost elements using the high-low method. Fixed costs
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT