Constructing and Assessing Income Statements Using Cost-to-Cost
Method
On March 15, 2012, Frankel Construction contracted to build a
shopping center at a contract price of $120 million. The schedule
of expected (which equals actual) cash collections and contract
costs follow ($ millions):
Year | Cash Collections | Cost Incurred |
---|---|---|
2012 | $ 30 | $ 25 |
2013 | 50 | 20 |
2014 | 40 | 40 |
Total | $ 120 | $ 85 |
(a) Calculate the amount of revenue, expense, and net income for
each of the three years 2012 through 2014 using the cost-to-cost
method.
Rounding instructions: Round percentages to the nearest whole number. Use rounded percentages for remaining calculations. Round revenue and income to the nearest whole number.
Enter $ answers in millions.
Cost-to-Cost Method | ||||
---|---|---|---|---|
Year |
Costs incurred |
Percent of total expected costs |
Revenue recognized |
Income |
2012 | ?$ | ?% | ?$ | ?$ |
2013 | ?$ | ?% | ?$ | ?$ |
2014 | ?$ | ?% | ?$ | ?$ |
$85 | $120 | $35 |
(b) Which of the following statements best summarizes our conclusion about the usefulness of the cost-to-cost method for this company?
1.The cost-to-cost method is not useful because it does not provide information about the total revenues over the life of the project.
2.The cost-to-cost method is an acceptable method under GAAP for contracts spanning more than one accounting period.
3.The cost-to-cost method does not provide a good estimate of the revenue and income earned in each period.
4.The cost-to-cost method is not useful because it is so dependent upon the completion estimate used by the company and can be easily manipulated.